Fire door regulations for commercial buildings in the UK

Fire door regulations for UK commercial buildings: the Fire Safety Order 2005, the 2022 Regulations, Approved Document B, ratings, checks and records.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

UK law does not list which doors must be fire doors in a commercial building. The Regulatory Reform (Fire Safety) Order 2005 names a responsible person, requires a fire risk assessment, and requires fire doors to be maintained in working order. The Fire Safety (England) Regulations 2022 add fixed check schedules, but only for residential blocks.

  • Responsible personEmployer, occupier or owner, named in law
  • Fire Safety Order 2005Non-domestic premises, England and Wales
  • 2022 RegulationsFixed door checks for residential blocks, England only
  • EN 1634-1Fire test; E, EW or EI at 30, 60, 90 or 120 minutes

The Regulatory Reform (Fire Safety) Order 2005 and the responsible person

The Regulatory Reform (Fire Safety) Order 2005 is the main fire safety law for non-domestic premises in England and Wales: offices, shops, factories, schools, hospitals and the common parts of residential blocks. It does not list which doors must be fire doors. It names a responsible person and requires that person to assess risk and act on the findings.

Article 3 defines the responsible person: in a workplace, the employer, to the extent the workplace is under their control; elsewhere, the person in control of the premises in connection with a trade, business or undertaking, or the owner. In multi-let buildings the duties can be shared, and the law requires co-operation. The full definition is on legislation.gov.uk.

Three duties matter for fire doors. Article 9 requires a suitable and sufficient fire risk assessment, reviewed regularly and after significant change, with the findings recorded. The assessment decides where fire doors go: escape routes, compartment lines and higher risk rooms. Article 14 requires emergency routes and exits to be kept usable. Article 17 requires a suitable maintenance system so doors stay in working order and good repair.

The Fire Safety (England) Regulations 2022: which buildings they cover

The Fire Safety (England) Regulations 2022 came into force on 23 January 2023 under powers in the 2005 Order. They apply in England only, and their fire door duties in regulation 10 cover a defined group of buildings, not commercial premises in general.

Regulation 10 requires the responsible person for a building with two or more sets of domestic premises, and common parts used for evacuation, to give residents fire door information: keep doors shut when not in use, do not tamper with self-closing devices, and report faults immediately. New residents get it as soon as reasonably practicable after moving in; all residents at least once every 12 months.

For buildings above 11 metres with two or more sets of domestic premises, regulation 10 adds fixed schedules: best-endeavours checks of flat entrance fire doors at least every 12 months, and checks of communal area fire doors at least every 3 months. Records must be kept, including where access was refused, and the checks must confirm self-closing devices work. The full text is on legislation.gov.uk.

These fixed schedules apply to residential blocks, not to offices, shops or factories. For commercial premises there is no statutory inspection interval. The frequency comes from the fire risk assessment and the article 17 maintenance system. Busy doors on escape routes may need monthly visual checks; a quiet store room door far less. The law demands a system, not a calendar date.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

Approved Document B: fire safety for new and altered work

Where the 2005 Order governs buildings in use, the Building Regulations 2010 govern building work. Approved Document B is the official guidance supporting the fire safety requirements, B1 to B5, of Schedule 1 to the Building Regulations. It comes in two volumes: Volume 1 covers dwellings including blocks of flats; Volume 2 covers buildings other than dwellings, the one that matters for commercial projects in England.

Approved Document B is guidance, not law. It shows one way to meet the requirements for new buildings, extensions and material changes of use; a designer may follow another route but must still satisfy the building control body. For existing buildings it is background, not a retrospective duty. The 2005 Order is what an occupied building must comply with.

At handover, note regulation 38 of the Building Regulations 2010. Where Part B applies, the person carrying out the work must give fire safety information to the responsible person by completion or first occupation, whichever is earlier. The information covers the design and construction of the building and the services, fittings and equipment provided, so the responsible person can operate and maintain it with reasonable safety. In practice the fire door schedules, test evidence and installation details should arrive with the keys. Ask for them and file them where the next responsible person will find them.

Scotland and Wales: the short version

Scotland runs a separate regime: the 2005 Order does not apply there. Duties sit under Part 3 of the Fire (Scotland) Act 2005 and the Fire Safety (Scotland) Regulations 2006, where the equivalent of the responsible person is the duty holder. The principles match, but the detail differs, so Scottish premises should follow Scottish Government guidance.

Wales is simpler. The 2005 Order applies in Wales as well as England, so the responsible person duties above apply there too. The Fire Safety (England) Regulations 2022, despite extending to England and Wales on paper, apply in England only. Welsh building work follows the Building Regulations as they apply in Wales, with its own approved documents.

Fire door ratings: what E, EW and EI mean

A fire door rating comes from a furnace test to EN 1634-1. The door is built into a wall, one side is heated to a standard curve, and the test records how long the door holds back fire. The result is a classification: E for integrity, meaning flames and hot gases do not pass; EW for integrity plus limited radiated heat; EI for integrity plus insulation, meaning the unexposed face stays below set temperatures. Each is given in minutes: 30, 60, 90 or 120.

FD30 and FD60 are trade shorthand for 30 and 60 minutes of integrity, the same idea as E30 and E60. What matters is the test evidence behind the label, covering the complete doorset as installed: leaf, frame, seals, glazing and hardware together. A certificate for a leaf alone does not cover the door on site.

Third-party certification, such as the LPCB LPS 1056 scheme for fire doors, gives ongoing assurance that production matches the tested design. Ask for the test evidence and the certification schedule, and check your sizes, configurations and hardware fall inside the certificated scope. Our fire ratings guide explains the classifications in full.

Self-closing devices and signage

A fire door only works if it is closed when fire breaks out, so doors on escape routes and compartment lines need a closer matched to the door’s size and weight. Check it: open the door to several positions and confirm it closes fully and latches every time. A door that is wedged open has no fire performance at all.

Hold-open devices linked to the fire alarm are the accepted alternative where a door must stay open in normal use. They release on alarm and let the closer shut the door. Anything else that keeps a fire door open is a maintenance failure: record it and put it right.

Fit clear fire door signs where the door must stay closed or be kept clear, on both faces where occupants approach from either side. Replace missing or damaged signs during routine checks.

Records to keep

Keep the fire risk assessment and its reviews, noting where doors were identified as control measures. Keep the Regulation 38 handover information from any building work, including door schedules and test evidence. Keep maintenance and inspection records with dates, findings and actions taken.

Where the 2022 Regulations apply, keep the records regulation 10 requires: the steps taken to check flat entrance doors, including where access was not granted, and the quarterly communal door check results. Keep training records for the people who carry out checks. Store everything where a successor can find it.

What the regulations do not cover

The 2005 Order names a responsible person and demands a risk assessment and a maintenance system, but it does not list which doors must be fire doors. That decision sits in the fire risk assessment, room by room, and two buildings that look alike can reach different answers.

The Order sets no statutory inspection interval for commercial premises. The quarterly and annual schedules in the 2022 Regulations cover residential blocks above 11 metres in England, and they do not extend to offices, shops or factories. A facilities manager who copies those dates onto a commercial estate is following a rule that does not apply to the building.

Approved Document B is guidance, not law. It shows one way to meet the building regulations for new work and material changes of use. For a building already in use it is background, and the 2005 Order is what the occupied building must comply with.

The regulations also say nothing about who must carry out the work. They demand a suitable system and competent people, but they do not name a qualification or a register. The responsible person must be able to show the system works, and that showing is the inspection record, the door schedule and the test evidence kept together.

The regulations also do not cover the wall around the door. A rated doorset set into an unrated partition leaves the compartment line only as strong as the partition, and no fire door regulation will catch that on its own. The fire risk assessment must look at the whole line, not the door alone.

Mistakes that leave a commercial building non-compliant

Most non-compliance is not a missing door. It is a door that was right on installation day and then lost its performance through small decisions. The six checks below catch the errors that appear most often.

  • Copying the residential check schedule onto commercial premises, so the risk assessment never sets its own interval.
  • Wedging a fire door open, or fitting a hold-open device that is not linked to the alarm.
  • Painting over intumescent seals, so they cannot expand when heat reaches them.
  • Swapping a closer, lock or hinge for a part with no fire test evidence.
  • Losing the Regulation 38 handover information, so the next responsible person cannot prove what was installed.
  • Treating Approved Document B as the law for an existing building, and missing the duties the 2005 Order actually sets.

Each of these is cheap to prevent and costly to fix after an incident or an enforcement visit. Fix the interval in the fire risk assessment, not in a diary. Write the inspection dates, the person responsible and the record location into the same document, and review them whenever the building changes use, the layout changes or a door is replaced. A system that survives a change of responsible person is the one that was written down. For the checks themselves, see the fire door inspection checklist, and for what the ratings mean, see the fire ratings page. Where an opening also needs forced entry resistance, see the dual certification guide.

The periods the shared parts must hold: what the order names for each door

The shared parts of a commercial building take the periods the regulation names, and each door on the route takes the period the part of the building it guards demands. A stair core takes the period the escape route needs, a corridor takes the period the compartment wall needs, and a plant room takes the period the fire load behind it demands. The period on the order follows the room behind the leaf, not the size of the leaf, because the fire load behind the leaf decides how long the doorset must hold.

EN 1634-1 measures fire resistance in E, EW and EI from 30 to 120 minutes, and the letters beside the number say what the doorset held back. E stops the flames, EW stops the flames and some of the heat, and EI stops both the flames and the heat. The letters belong on the order beside the period.

The leaf, the frame and the seals faced the test as one doorset, and the proof covers the doorset as one. A leaf changed after the test leaves the door different from the one that was proved, and a door that differs from the test has no proof. The closer that pulls the leaf shut takes a power size of at least EN 3 to BS EN 1154 on a fire door, because a leaf that stands open holds nothing back.

The gap round the leaf is held to 4 mm, wide enough for the leaf to swing and narrow enough to hold smoke back. An intumescent seal swells at around 200 to 250 degrees, and paint over the seal stops it swelling, because the paint skin holds the seal flat while the heat rises. A gap that has widened or a seal that has come away goes into the record beside the door.

The proof that follows the door: what the file must hold after handover

The proof that follows the door is the test report that names the rating and the product it was proved on, because a rating without the product it was proved on proves nothing. The file that holds the proof lives with the building, and it names every door, the period each one carries and the test report behind it. A door with no paper behind it is a door whose period no one can prove.

Changes after handover break the proof the test left behind, because a lock changed, a closer swapped or a seal painted leaves the doorset different from the one tested. Each change goes into the record beside the door it belongs to, so the record shows the door as it stands, not as it was tested. A change with no note beside it leaves the rating unproved.

The visit that looks after the shared parts goes through the building door by door and looks at the leaf, the gaps, the seals, the closer and the lock on each one. Every fault goes into the record on the day it is found, beside the door, the part and the date, so the repair is ordered while the fault is still small and the door never stands open.

Position Period What the doorset must prove What to check
Stair core EI 60 Flames and heat for 60 minutes Leaf, closer, seals
Corridor EI 30 Flames and heat for 30 minutes Leaf, gaps, seals
Plant room EI 60 Flames and heat for 60 minutes Leaf, seals, gap
Store EI 30 Flames and heat for 30 minutes Leaf, closer, lock
Entrance lobby EI 30 Flames and heat for 30 minutes Leaf, glass, lock

What each visit should look for is set out in the fire door inspection checklist, and what breaks a rating once a door is fitted is set out in keeping an LPS 1175 rating valid guide. The sizes and the fitting of closers are covered in the fire door closers guide, and the columns the schedule needs are set out in how to specify security doors guide.

Steel fire doors that also carry a security rating

Some openings need both fire and forced entry resistance: plant rooms, server rooms, cash handling areas and risers. The answer is a dual rated doorset, one construction tested to EN 1634-1 for fire and to LPS 1175 for forced entry, with both ratings on the same test evidence.

The level follows the threat. SR2 fire doors (B3, 3 minutes against category B tools) suit commercial and communal buildings. SR3 fire doors (C5, 5 minutes against crowbars, drills and chisels) suit cash handling rooms and higher risk plant. SR4 fire doors (D10, 10 minutes against category D tools) suit critical infrastructure. The two ratings are separate results from separate tests on the same construction, so ask for both certificates against the same doorset reference. Our dual certification guide works through the detail.

Dual rating is not always needed. A dual rated doorset is heavier, needs a stronger frame and fixings, and needs more careful installation. Where the threat is fire alone, a well specified fire rated steel door is the right and economical choice. Sectors with mixed risks, such as education and healthcare, are where dual rating earns its place. Compare the levels in our SR2 vs SR3 vs SR4 guide, and use our fire door inspection checklist to keep them in working order. The wider guides library covers the rest of the range.

Law Applies to Fire door duty Reference
Regulatory Reform (Fire Safety) Order 2005 Non-domestic premises, England and Wales Risk assessment, suitable maintenance system, usable escape routes Articles 9, 14, 17
Fire Safety (England) Regulations 2022 England only; residential blocks with 2 or more domestic premises Resident information; 3-month communal and 12-month flat door checks above 11 m Regulation 10
Building Regulations 2010 New work and relevant changes of use where Part B applies Fire safety information to the responsible person by completion or first occupation Regulation 38
Fire (Scotland) Act 2005 Scotland Duty holder regime with risk assessment and maintenance duties Part 3

Do not mix up the check schedules. The 3-month and 12-month checks in the 2022 Regulations apply to residential blocks in England above 11 metres. For offices, shops and factories the check frequency comes from the fire risk assessment, not from a fixed statutory interval.

Who is the responsible person in a rented office?

In a workplace it is the employer, to the extent the workplace is under their control. In multi-let buildings the landlord or managing agent may hold duties for common parts, and the law requires co-operation. A lease cannot remove the statutory duty.

How often must fire doors be checked in a commercial building?

The Order sets no fixed interval. Article 17 requires a suitable maintenance system, and the fire risk assessment sets the frequency. Record every check. Residential blocks are different: the 2022 Regulations require 3-monthly communal and 12-monthly flat entrance checks above 11 metres.

Do the Fire Safety (England) Regulations 2022 apply to my office?

No. They apply in England only, and regulation 10 covers buildings with two or more sets of domestic premises. Commercial premises follow the 2005 Order.

What does FD30 mean, and how does it differ from EI30?

FD30 is trade shorthand for 30 minutes of fire integrity. In the EN 1634-1 classification that is E30. EI30 adds insulation: the unexposed face must also stay below set temperatures. Your fire strategy decides which class each opening needs.

What paperwork should I hold for each fire door?

Test evidence and the certification schedule for the doorset as installed, the Regulation 38 handover information, and ongoing maintenance records. Keep them where the next responsible person can find them.

Planning fire doors for a commercial building?Send us the ratings, sizes and hardware you need for a tested steel doorset quote.
Get a free quote

Related

More in guides for specifiers

10 mistakes when specifying certified security doors 10 steps to specify an LPS 1175 door Acceptance and Snagging of a Security Door or Barrier Job Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Depots Explained Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Doors and Gateway 2 in Higher-Risk Buildings Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to keep an LPS 1175 door rating valid after installation How to Specify Fire Doors in a Housing Tender How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Programming a Security Door and Barrier Package on a Live Site Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Server Room Doors Explained Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →

Products

One supplier for the whole building envelope

Ready to specify your project?

Free assessment, written specification and test evidence. Reply within one working day.