Programming a Security Door and Barrier Package on a Live Site

A door and barrier package is a sequence, not a shopping list. Survey first, order second, foundations before barriers, and handover last of all.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

A door and barrier package is a sequence, not a shopping list. Survey first, order second, foundations before barriers, and handover last. This guide sets out the order and why it matters.

  • SurveyWhat the site really holds
  • OrderPlaced on measured openings
  • FoundationsFirst in the ground, first to cure
  • HandoverThe record the next person needs

Survey before the order

Nothing should be ordered until the site has been measured. The survey settles the openings, the structure around them, the ground the barriers will fix into, the access routes for delivery, and the services buried where a foundation will go. A door ordered from an unchecked drawing may not fit its opening.

The NPSA guidance on hostile vehicle mitigation places the practical site assessment at the heart of the requirement: a detailed review of the vulnerabilities and opportunities in the environment, in operational security and in physical security measures. That review is the survey in its widest sense, and it belongs before the requirement is fixed.

Measure every opening, not a sample of them. Openings in one building differ by a few millimetres, and a doorset made for one may not fit the next. Note the wall the frame bolts into and anything added since the drawings were made. The security doors specification guide sets the scope in the order from the start.

The order follows the survey

Place the order on the survey, not on the drawings. The order should name the product, the size as measured, the hardware, the fixings, and the rating the threat assessment calls for. A rating chosen before the survey is a rating chosen for a site nobody has walked.

Agree the sequence in the order as well as the products. Name which openings come first, which barriers need foundations, and what must be ready before each stage starts. A supplier who knows the sequence can plan the work.

Check the listing before ordering, not after the products arrive. The LPS 1175 certificate guide explains the Red Book Live check, and the tender response checklist shows the supplier view. The public frameworks guide covers how the order is placed on a framework.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

Foundations first, and the wait that follows

Barriers go into the ground first, and the ground work sets the pace of the package. The NPSA foundation guidance sets out three types: deep foundations, more than half a metre below the ground, shallow foundations, half a metre or less, and surface foundations, fixed to the ground or standing free with no digging at all. The type follows the ground, the services under it, and the rating the barrier must hold.

A foundation must match the tested conditions, or go further than them. The NPSA guidance says the installation should match or exceed the tested conditions, and where the site forces a bespoke foundation, a suitably qualified engineer should validate the change. Digging a shallower foundation because the programme is short is a new build with no test behind it.

Then comes the wait. The NPSA curing guidance says a standard mix reaches about 60 per cent of its strength within three days and about 75 per cent after seven days, with the strength quoted at 28 days. A range of 10 to 30 degrees is preferred; below 5 degrees the process practically stops. Do not pour onto snow or frozen ground, and adding water to a stiff mix weakens the result. Plan the programme around that wait. The bollard foundations guide sets out what the rating needs below the pavement.

Doors once the openings are ready

Doors follow the openings, not the delivery date. An opening is ready when the structure is sound, the dimensions match the survey, and the wall can take the fixings. A doorset fitted into an opening that is still being built will be fitted twice.

Fixing is part of the rating, and a doorset fixed badly is not a rated installation. The fixings, frame and seals must follow the tested method. Check each opening against the drawing before fixing begins.

Ask for the installer’s listing before the work starts, and check it on Red Book Live. The product listing and the installer listing are separate entries; one is no substitute for the other. The LPCB installer scheme asks the installer to issue a Certificate of Conformity for each installation. The installation handover guide lists the checks for the day the product arrives on site.

Keeping a live site open

Most packages land on a site that stays open while the work runs. The site must stay protected at every stage, not only when the work is finished. The NPSA guidance asks for the scheme to fit the site’s normal operations, with vehicle access control and emergency access planned as parts of it.

Work in phases, and hand each phase over before the next begins. A phased programme lets one entrance stay protected while another is rebuilt, and gives the site a working line at every point. Name the phase boundaries, and what must be true before the next phase starts.

Plan for the people who use the site, not only for the work. Deliveries, visitors, staff and emergency vehicles all need a route while the work runs. A programme that forgets the people who use the site will be stopped by them. The ten mistakes guide lists the errors buyers keep making.

Commissioning before anyone signs

Commissioning is the step that turns fitted products into a working package. Run every operable unit through its full movement, test every lock and control, and check that the access system lets the right people through and keeps the wrong people out. A unit that has never been run through its movement has never been proved, whatever its certificate says.

Test the failures as well as the successes. Cut the power and check the manual release. Sound the alarm and check the hold-open devices release. Try the emergency route the fire service would use. A package that only works when everything is normal has not been commissioned; it has only been switched on.

Write down what was tested and what the result was, unit by unit. The commissioning record is the last evidence before handover; without it, the next person trusts what nobody measured. When a stage slips, re-plan the sequence rather than compressing it. The Gateway 2 guide covers that same discipline, applied to fire doors in higher-risk buildings.

Stage What happens What must be true first
Survey Openings, ground, services measured Drawings and access in hand
Order Products named on measured sizes Survey complete, listing checked
Foundations Dig, pour, cure Services mapped, engineer signed
Doors and barriers Fix, seal, set Openings ready, concrete cured
Commissioning Run, test, record Every unit fitted and powered
Handover Record passed on, receipt signed Commissioning record complete

Handover: the record the next person needs

Handover is the day the evidence passes to the person who will run the building. For a higher-risk building, the gov.uk golden thread guidance says what that evidence must hold. The client hands over the papers the building control application rested on, the papers behind the completion certificate application, the certificate itself, the means to reach and control the building information, and the fire safety information for the Responsible Person.

Whoever takes the record signs to say it arrived and can be used. That signature matters: the next person needs the record on the day a fault appears, not on the day someone finds the password.

Keep the record in one place, in digital form, guarded against unauthorised access, with version control, so the next person finds the truth in one file. The same discipline serves any package: the test evidence, the installation record, the commissioning record, and every maintenance visit after, all in one place. The golden thread records guide lists the fire door records that belong in the thread. The barrier care guide shows what happens to the line once it is in service, and the Vehicle Dynamics Assessment guide shows how the threat was worked out.

A package is finished when the record is handed over, not when the last unit is fitted.

What should be surveyed before the order?

Measure each opening, the wall beside it, the ground under the barriers, the way deliveries reach the site, and the services under any foundation. A door ordered from unchecked drawings can arrive to find its opening is a different size.

How long does a barrier foundation need?

Three days gives about three-fifths of the quoted strength, seven days about three-quarters, and the quoted figure itself is the 28-day one. Hold the programme to those marks, and keep loads off the pour.

Can doors be fitted while the site stays open?

Yes, when the work is phased so each entrance is rebuilt in turn while the others stay protected. Agree the boundaries of each phase in advance, with the conditions that open the next one.

What does handover need for a higher-risk building?

The papers behind both applications, the certificate itself, and the fire safety information. The person who takes the record signs for receipt.

What happens when a stage slips?

Change the plan, not the standards. Shift a phase or move the handover date, and keep the curing wait and the commissioning tests intact.

Planning a door and barrier package?Send the site, the openings, and the dates the work must fit around.
Contact us for a free quote

Related

More in guides for specifiers

10 mistakes when specifying certified security doors 10 steps to specify an LPS 1175 door Acceptance and Snagging of a Security Door or Barrier Job Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire door regulations for commercial buildings in the UK Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Depots Explained Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Doors and Gateway 2 in Higher-Risk Buildings Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to keep an LPS 1175 door rating valid after installation How to Specify Fire Doors in a Housing Tender How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Server Room Doors Explained Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →

Products

One supplier for the whole building envelope

Ready to specify your project?

Free assessment, written specification and test evidence. Reply within one working day.