CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed
Fitting a security door, shutter or barrier is construction work. The client, principal designer and principal contractor each hold named duties under CDM 2015.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
Fitting a security door, a shutter or a vehicle barrier is construction work, and the Construction (Design and Management) Regulations 2015 set out who must do what before and during the work. The client, the principal designer and the principal contractor each hold named duties.
- ClientArrangements
- Principal designerPre-construction
- Principal contractorConstruction phase
- Construction phase planBefore work starts
When the Regulations apply to a door, shutter or barrier job
The Construction (Design and Management) Regulations 2015 came into force on 6 April 2015, replacing the 2007 Regulations. They apply to all construction work in Great Britain.
The client is any person for whom a project is carried out. A commercial client is an organisation or individual for whom a construction project is carried out as part of a business. A domestic client has work done on their own home, or a family member’s home, outside a business, and their duties normally pass to the contractor, principal contractor or principal designer under a written agreement.
One person can hold more than one role. The HSE summary of duties says organisations or individuals can carry out the role of more than one duty holder, provided they have the skills, knowledge, experience and organisational capability each role needs. The planning permission guide lists the checks for shutters, gates and bollards.
The client and the arrangements for the project
Regulation 4 says a client must make suitable arrangements for managing a project, including the allocation of sufficient time and other resources. Arrangements are suitable where they ensure the work can be carried out without risks to the health or safety of any person affected by the project, and where the Schedule 2 facilities are provided. The client must maintain and review the arrangements throughout the project.
The client must provide pre-construction information as soon as is practicable to every designer and contractor appointed, or being considered for appointment. The principal designer assists the client with that information. Before the order is signed, the tender response checklist guide puts the questions a buyer should ask in one place.
The client must also ensure that a construction phase plan is drawn up before the construction phase begins, and that the principal designer prepares a health and safety file. The lead times guide gives a date to each stage, from survey through manufacture to fitting. A new doorset also has a thermal limit to meet, and the thermal and weather guide names the U-value limits for buildings other than dwellings.
Appointing the principal designer and the principal contractor
Regulation 5 says that where there is more than one contractor, or it is reasonably foreseeable that more than one will be working on a project, the client must appoint in writing a designer with control over the pre-construction phase as principal designer, and a contractor as principal contractor. The appointments must be made as soon as is practicable, and before the construction phase begins.
The trigger is the number of contractors, not the size of the job. A door replacement using a surveyor, a fitter and an electrician can pass the trigger, so the client should count the firms on the job first. The programming guide orders the stages of a door and barrier package, from survey to handover.
Where no principal designer is appointed, the client must carry out those duties in regulations 11 and 12. Where no principal contractor is appointed, those duties in regulations 12 to 14 fall to the client. The client must take reasonable steps to ensure the principal designer and the principal contractor comply with their duties.
The principal designer and the pre-construction phase
Regulation 11 says the principal designer must plan, manage and monitor the pre-construction phase and coordinate health and safety matters during that phase, so far as is reasonably practicable, so the project is carried out without risks to health and safety. The principal designer must take into account the general principles of prevention, and where relevant the construction phase plan and health and safety file.
The principal designer must identify and eliminate or control, so far as is reasonably practicable, foreseeable risks to people carrying out or affected by construction work, people maintaining or cleaning a structure, and people using it as a workplace.
Designers carry their own duties under regulation 9. A designer must not commence work unless satisfied the client is aware of the client duties, and when preparing or modifying a design must work from the general principles of prevention and any pre-construction information. Where a risk is left after elimination, the designer must reduce or control it, tell the principal designer, and put the information in the health and safety file.
The construction phase plan
Regulation 12 says that during the pre-construction phase, and before setting up a construction site, the principal contractor must draw up a construction phase plan. The plan must set out the health and safety arrangements and site rules, and must include specific measures for Schedule 3 work where applicable.
The principal designer must assist the principal contractor with all relevant information it holds, including pre-construction information and information from designers under regulation 9(3)(b). Throughout the project the principal contractor must review, update and revise the plan.
A single-contractor job still needs a plan. Regulation 15 says that where there is only one contractor, that contractor prepares the construction phase plan before setting up a construction site, and the plan must fulfil regulation 12(2). The replacement guide walks through a door swapped in an occupied building, where the plan must cover the people still using it.
The principal contractor and the construction phase
Regulation 13 says the principal contractor must plan, manage and monitor the construction phase, keeping the work free of risks to health and safety so far as is reasonably practicable. The principal contractor must organise cooperation between contractors, including successive contractors on the same site, and coordinate the legal requirements that apply.
The principal contractor must ensure a suitable site induction is provided, that unauthorised persons are kept out, and that Schedule 2 facilities are provided throughout the construction phase. Regulation 14 says the principal contractor must arrange for workers to cooperate in developing, promoting and checking health and safety measures, and must consult workers or their representatives.
Contractors follow the plan. Regulation 15 says that where more than one contractor is working on a project, a contractor must comply with directions given by the principal designer or the principal contractor, and with the relevant parts of the construction phase plan. A contractor must not employ a person on a construction site unless that person has, or is in the process of obtaining, the necessary skills, knowledge, training and experience. After an attack, the checks the forced entry guide sets out need the same written record.
Notification and the health and safety file
Regulation 6 says a project is notifiable where the work is scheduled to last longer than 30 working days and have more than 20 workers working simultaneously at any point, or to exceed 500 person days. Where a project is notifiable, the client must give notice in writing to the Executive as soon as is practicable before the construction phase begins. The notice must contain the particulars in Schedule 1, be clearly displayed in the construction site office, and be updated where necessary.
The health and safety file is the record that outlives the job. Under regulation 12, the principal designer must prepare a file appropriate to the project, with information likely to be needed during any subsequent project. The file must be reviewed, updated and revised as the work requires, and at the end of the project the principal designer, or the principal contractor where there is no principal designer, must pass it to the client.
The file and the fire safety information are different records. The health and safety file serves the next construction project, while the Regulation 38 pack serves the person who runs the building. The Regulation 38 guide sets out what the responsible person receives, and the golden thread guide deals with the digital record a higher-risk building keeps. The commissioning and handover guide lists the papers a door should carry. The installation handover guide goes opening by opening through the buyer’s checks.
| Duty holder | What the Regulations ask | Regulation |
|---|---|---|
| Client | Suitable arrangements, time, resources, information | Regulation 4 |
| Principal designer | Coordinates the pre-construction phase | Regulation 11 |
| Principal contractor | Prepares the plan, runs the phase | Regulations 12 and 13 |
| Contractor | Plans its own work | Regulation 15 |
| Designer | Reduces foreseeable risks through design | Regulation 9 |
The duties start before the first fixing is drilled. Appoint the right people, draw up the plan, and keep the file current.
Does CDM 2015 apply to fitting one security door?
Yes, where the work is construction work. The duties scale with the job. A job with one contractor still needs a plan under regulation 15.
When must a principal designer and principal contractor be appointed?
Where more than one contractor works on the project, or where a second contractor is expected to join it. The client appoints both in writing before the work begins.
Who draws up the construction phase plan?
The principal contractor, during the pre-construction phase and before the site is set up. With one contractor, that contractor prepares the plan.
When is a project notifiable to HSE?
Where the job runs longer than 30 working days with more than 20 workers on site at the same time, or passes 500 person days. The client must send written notice to the Executive first.
What happens to the health and safety file?
The principal designer prepares it during the pre-construction phase, keeps it updated, and passes it to the client at the end of the project.
Contact us for a free quote
Related
More in guides for specifiers
Products
One supplier for the whole building envelope
Ready to specify your project?
Free assessment, written specification and test evidence. Reply within one working day.