10 mistakes when specifying certified security doors

Ten security door specification mistakes: rated leaves in unrated frames, wrong issues, substituted hardware. Why each matters and the fix, for UK specifiers.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

Most security door failures trace back to the specification, not the product. A rated leaf means little in an unrated frame, and the wrong issue of a standard can void the evidence you rely on. Here are ten mistakes specifiers make, why each one matters, and how to fix it before the order goes out.

  • Ten mistakesEach one with why it matters and how to fix it.
  • Doorset thinkingThe rating covers the tested assembly, not the leaf alone.
  • EvidenceTest reports must match the configuration ordered.
  • Fix earlyEvery mistake below is cheaper to fix on paper than on site.

The ten mistakes at a glance

The table summarises all ten. Each numbered section below explains the mechanism and the fix in full.

# Mistake What goes wrong
1 Rated leaf, unrated frame The assembly was never tested as built
2 Wrong issue of the standard The rating cited does not match the evidence
3 Substituted hardware The tested set is gone, and so is the rating
4 Weak surrounding wall The attack goes around the door
5 Glazing never tested in the door The vision panel becomes the weak point
6 Fire rating ignored Security upgrades void the fire performance
7 No certification scheme named Nobody can verify the claim
8 Access control left for later Electric hardware clashes with the rated build
9 Access route forgotten The doorset cannot reach its opening
10 No evidence at handover Nobody can prove what was installed

The rating belongs to the doorset. Test evidence covers the leaf, frame, hardware, glazing and fixings as one assembly. Change any element and the rating no longer describes what is on site.

1. A rated leaf in an unrated frame

Why it matters. The test attacks the whole doorset: leaf, frame, hinges, locks and fixings together. A D10 leaf hung in a lightweight frame fails at the frame long before the leaf is troubled, and no test report covers that combination. The rating on the leaf certificate does not transfer to the assembly on site, so the money spent on the leaf buys no proven performance.

The fix. Specify the doorset as one rated assembly from a single source. Ask for test evidence that names the frame alongside the leaf, and reject any proposal that splits them between suppliers. Security doors are supplied as complete rated assemblies, which is the pattern to insist on in every clause.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

2. Citing the wrong issue of the standard

Why it matters. Standards are revised and ratings move with them. LPS 1175 Issue 8 replaced the SR1 to SR8 scale with classes A1 to H20, so a clause that just says “SR4” can be answered with evidence to a superseded issue. The client believes they bought current performance while the paperwork describes something older, and the gap only surfaces during an audit or after an incident.

The fix. Always cite standard, issue, class and scheme in one breath: “LPS 1175 Issue 8.2 (September 2024), D10”. Check that the test evidence cites the same issue before the order goes out. Our LPS 1175 guide maps the old and new scales so the clause cannot be misread.

3. Letting hardware be substituted on site

Why it matters. The rating was earned with a specific hardware set. When a contractor swaps the specified lock case or cylinder for an “equivalent” during installation, the tested configuration stops existing. This is the most common way ratings die between specification and handover, and it is almost never documented, so nobody knows the evidence is gone.

The fix. Schedule hardware as named sets and require written approval for any substitution, with evidence that the replacement keeps the rating intact. Make the door supplier confirm the as-fitted set at handover, in writing, against the schedule.

4. Ignoring the wall the door fixes into

Why it matters. Attackers take the easiest route available. A D10 doorset fixed into lightweight block or an unlined stud wall can be defeated by attacking the wall beside the frame. The door holds while the building gives way, which means the specification protected the opening and forgot the room around it.

The fix. State the minimum wall construction in the specification and detail the frame fixings into it. Where the wall is weak, upgrade the wall or add a rated screen around the opening. SR3 and SR4 doorsets show the fixing details that a serious specification asks for.

5. Adding glazing that was never tested in the door

Why it matters. A vision panel changes the leaf: it cuts the steel, adds a bead system and introduces glass with its own behaviour under attack. Glazing that carries a rating on its own, such as LPS 1270 security glazing, does not automatically keep that rating once it is fitted into a forced-entry doorset. The combination needs its own evidence, and without it the vision panel is the weak point.

The fix. Specify glazing as part of the doorset, not as a separate line item. Ask for test evidence covering the exact leaf, bead and glass build-up. If the evidence does not show the combination, treat the vision panel as unrated, whatever the glass certificate says.

6. Forgetting the fire rating

Why it matters. Security hardware and fire performance can conflict. A heavy lock case, an extra fixing or a different seal can change how the leaf behaves in a fire test, and a closer removed for convenience can void the fire rating entirely. The door ends up secure but non-compliant, which neither building control nor the insurer will accept.

The fix. Where both performances are needed, specify a combined doorset with evidence for each on the same assembly, such as our fire and security doors. The fire ratings guide explains how E, EW and EI classifications work. Never let site changes touch the hardware without checking both sets of evidence first.

7. Naming no certification scheme

Why it matters. “Tested to LPS 1175” with no scheme behind it is a claim with no audit trail. Third-party certification means ongoing factory checks, not a single test carried out long ago. Without a named scheme, the client has no way to confirm that the door delivered matches the door that was tested.

The fix. Name the scheme in the clause and ask for the listing or certificate number. Verify it before accepting the doorset, and file the document with the building records where the facilities team can find it.

8. Leaving access control to coordinate later

Why it matters. Electric strikes, maglocks and readers need cable routes, reinforced mounting points and power supplies designed into the leaf. When access control is specified after the door is ordered, installers cut into a finished, rated leaf, and every cut is a compromise the test never saw. The door still locks, but the rating is guesswork.

The fix. Schedule the access control devices with the door, name who supplies and wires each part, and get the device list to the door manufacturer before fabrication. On healthcare projects, where locking also serves safeguarding, this coordination decides whether the door is usable on opening day.

9. Measuring the opening but forgetting the access route

Why it matters. A rated doorset is heavy, and the route to the opening matters as much as the opening itself. Narrow corridors, tight stairwells, weight-limited floors and restrictions on lifting equipment have all stopped installations on the day. A door that cannot reach its opening becomes an expensive delay with the programme already running.

The fix. Survey the route as well as the opening: record corridor widths, stair turns, lift capacities and any restrictions on delivery vehicles. Agree the delivery and lifting plan before manufacture, not on the morning of installation.

10. Accepting the doorset with no test evidence

Why it matters. Without the test report, the scheme listing and the installation records, nobody can prove what was fitted. The next lock change, the next audit and the next insurance review all become guesswork. The rating exists only on the invoice, which protects nobody.

The fix. Make evidence a condition of acceptance: the test report for the exact configuration, the certification listing, the as-fitted hardware schedule and the installation records. Our specification checklist shows how to write this into the contract, and the cost factors guide explains why evidence is worth paying for. Browse all guides for related topics.

What the handover pack should hold

A doorset is accepted on its evidence, not on its looks. The handover pack should hold the test report and the classification for the complete assembly, the fire classification to EN 1634-1 where the doorset must hold fire, and the hardware schedule naming every part fitted to the leaf. A pack that holds only a delivery note has proved nothing, and a doorset accepted without its evidence is a doorset nobody can speak for.

The fire evidence belongs in the same pack. A door marked FD30 carries 30 minutes of integrity to EN 1634-1, and a door marked FD30S carries 30 minutes of integrity plus smoke control to BS EN 1634-3. The smoke rating matters because a fire rating on its own does not prove smoke control, and smoke passes through a cold gap long before heat reaches the seals. Ask for the smoke evidence by name where the fire strategy asks for it.

The fitting record belongs in the pack too. The fixings used, the gaps achieved around the leaf and the wall the frame fixes into should all be written down, because a rated leaf in an unrated wall gives an unrated opening. Our how to specify security doors guide works through the schedule column by column, and our fire door inspection checklist gives the checks that catch a failing leaf before it matters.

What to do when a mistake is found on site

Stop and record the mistake before anyone tries to fix it. Photograph the door, measure the gap, write down the hardware fitted and the hardware named in the evidence, and note the date and the person who found it. A record made on the day is a record the next person can use, and a mistake found without a record is a mistake that will be argued about later.

Do not improvise a fix. A closer swapped for a different model, a lock changed for one never tested in the leaf, or a leaf trimmed to fit a frame that moved all break the tested construction, and a change that is not in the evidence should not be made. Ask for the evidence when a change is proposed, not after it is made, and wait for the fresh evidence before the work goes ahead.

A rating cannot be added after the doorset is fitted. Fitting stronger locks to an untested door does not make it a D10 doorset, because that combination was never attacked in a test, and a door that needs a rating must be replaced with a tested doorset. A SR2 rated steel door resists three minutes of attack with tools such as screwdrivers, pliers and hand saws, and D10 covers ten minutes with sledgehammers, disc cutters and jigsaws. Order the tested doorset, and file the evidence with the building records where the next responsible person will find it.

Mistake found First step Who decides
Wrong hardware fitted Record the part fitted and the part named The specifier, with fresh evidence
Leaf trimmed on site Measure the leaf and the opening The supplier, before any further work
Gap wider than 4 mm Measure all four sides with a gap gauge The installer, with the cause named
No test evidence at handover Refuse acceptance until the pack arrives The responsible person

Keep the evidence with the doors. The test report, the classification, the hardware schedule and the fitting record should travel with the doorset, and a building that can show its checks, its faults and its fixes has a maintenance system behind its doors.

The schedule the fitter works from: every part named once

The schedule is the one document every door on the job is ordered from, and a line that names only the leaf leaves the frame, the hardware and the evidence to be guessed on site. Each line should name the leaf, the frame, the hardware by model, the rating with its standard and issue, and the evidence that proves it, so the door that arrives is the door the schedule asked for.

The standard needs its issue beside its name, because LPS 1175 Issue 8.2 is the current issue and an order that names only LPS 1175 leaves the issue to be guessed. The same holds for the fire proof, where EN 1634-1 needs its minutes and letters beside it, so FD30 and FD60 are never written as bare numbers with no letters.

Hardware should be named by model, not by type, because a closer named only as a closer can be swapped on site for a closer never tested in the leaf. The schedule names the closer, the lock, the hinges and the seals by model, and the hardware schedule travels with the order so the fitter can check each part against the line it belongs to.

The evidence should be named on the schedule too, because a test report named only as test evidence cannot be checked against the doorset it proves. The schedule names the report and the classification for the complete assembly, leaf, frame and hardware together, so the handover pack can be checked line by line when the doors arrive.

The opening the schedule forgot: the wall and the access route

The wall the frame fixes into decides whether the rating holds, because a rated leaf in an unrated wall gives an unrated opening. The schedule should name the wall beside each opening, with its construction and its fire rating where the door must hold fire, so a leaf ordered for a masonry wall is never fitted into a stud wall that was never proved.

The access route decides whether the leaf can be used at all, because a door that opens onto a step or a narrow corridor fails the people who must pass through it. The schedule should name the route beside the opening, with the clear width and the level threshold, so the leaf that arrives fits the route it guards.

The delivery route matters too, because a leaf wider than the corridor it must travel down cannot reach its opening. The schedule should name the route the leaf takes from the delivery bay to the opening, so a leaf ordered for a plant room at the end of a narrow corridor arrives in pieces the fitter can carry, or not at all.

Schedule line What it names What to check When
Leaf and frame Rating, standard and issue Report names the assembly Before the order
Hardware Closer, lock, hinges, seals by model Model matches the evidence Before the order
Wall Construction and fire rating Leaf suits the wall Before the order
Access route Clear width, level threshold Leaf fits the route Before the order
Evidence Test report and classification Pack checked line by line At handover

The schedule column by column is worked through in the how to specify security doors guide, and the checks that catch a failing leaf are set out in the fire door inspection checklist. What can break a rating once a door is fitted is named in the keeping an LPS 1175 rating valid guide, and the doors that must hold both fire and forced entry are covered in the security door maintenance checklist.

Frequently asked questions

Can a door be upgraded to a rating after it is installed?

No. A rating describes a tested assembly, not a collection of parts. Fitting stronger locks to an untested door does not make it a D10 doorset, because that combination was never attacked in a test. If you need a rating, replace the doorset with a tested one.

Is PAS 24 enough for a commercial building?

PAS 24 is written for residential doors and windows and sits below LPS 1175 on the threat scale. For commercial, cash-handling or critical sites, specify LPS 1175 to a class matched to the threat assessment instead.

What is the difference between SR ratings and the letter classes?

SR1 to SR8 was the old LPS 1175 scale. Issue 8 replaced it with classes A1 to H20: B3 is the old SR2, C5 is SR3 and D10 is SR4. Always cite the current issue so the evidence matches the clause.

Who checks that the installation matches the test?

Your specification should say. Require installation to the manufacturer’s tested details, with records of the fixings used and the gaps achieved, and make the evidence a condition of acceptance. An independent check at handover closes the loop.

Do I need a new survey if the opening size changes?

Yes. The doorset is made to the surveyed opening, and the test evidence covers a stated size range. A changed opening can push the doorset outside its evidence, so re-survey and re-confirm before manufacture starts.

Want a second pair of eyes on your specification?Send your door schedule through the quote form and we will flag the gaps before they become site problems.
Get a free quote

Related

More in guides for specifiers

10 steps to specify an LPS 1175 door Acceptance and Snagging of a Security Door or Barrier Job Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire door regulations for commercial buildings in the UK Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Depots Explained Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Doors and Gateway 2 in Higher-Risk Buildings Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to keep an LPS 1175 door rating valid after installation How to Specify Fire Doors in a Housing Tender How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Programming a Security Door and Barrier Package on a Live Site Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Server Room Doors Explained Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →