Installation Handover: LPS 1175 Doors and PAS 68 Barriers
Handover is where the buyer checks that the product on site is the product that was tested. The installer, the certificate and the as-built record.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
A rating is proved in a test laboratory. Handover is where the buyer checks that what stands on site is what was tested. This guide walks through the checks.
- Certificate of ConformityThe installer’s proof for each job
- As-testedThe rating covers one build only
- As-builtThe record of what was fitted
- Golden threadThe handover record for higher-risk buildings
Start with the installer, not the product
The product certificate proves the product. It does not prove the fitting. A doorset that leaves the factory as a tested assembly can still lose its rating on site if it is hung in the wrong frame, fixed with the wrong fixings, or trimmed to fit an opening that moved.
LPCB runs installer schemes as quality assurance schemes. They comprise a technical assessment of the installer’s capability, approval and surveillance of the installer’s quality management system to ISO 9001, regular surveillance inspections of installations in progress, and listing in the Red Book. An installer scheme for sprinkler systems, LPS 1048 Issue 6.1, shows the shape: provisional approval first, full approval only after assessment.
Ask whether the installer holds an LPCB listing for the service it is selling, and check it on Red Book Live before the work starts. A product listing and an installer listing are two different entries, and one does not stand in for the other. The LPS 1175 certificate guide covers the checks on the product listing, and the vehicle barrier due diligence guide takes the same evidence habit to barriers.
The Certificate of Conformity for the install
Under the LPCB installer scheme structure, the installer issues a Certificate of Conformity for each installation. That certificate is the installer’s own statement that the work was done to the tested details, and it sits beside the product certificate in the handover pack. Ask for it by name before the work starts, so it is priced into the job rather than chased after the installer has left.
The certificate should name the site, the product as fitted, and the scope it covers. Read it against the order: the product name, the size, the hardware and the fixings should match what the order asked for. A certificate that names a different product, or a different size, is not evidence for the install on site.
Keep the certificate with the product certificate and the test report, in the building record. A rating that cannot be proved at handover cannot be proved later. The rating maintenance guide lists the things that can break a rating once the certificate is issued.
Match the installed door to the certificate scope
The scope is the boundary of the rating. It lists the sizes, the leaf arrangements, the options and the hardware that went through the test, and anything outside that list is outside the rating. A certificate for one leaf says nothing about two, and a certificate tied to one lock says nothing about another. Compare the fitted door with that list, item by item, before sign-off.
Start with the size, then the leaf arrangement, then the lock and the hardware, and compare the label on the product with the name on the certificate. The NPSA Manual Forced Entry Standard is written to be used with the British, European or International Standards that apply to the installation of the product under test, so the fitting standard matters as much as the product standard.
If anything on site falls outside the list, stop. A door that differs from its certificate is a different product, with no rating to show. Change the door, or get a certificate that covers the door as fitted, before the handover is signed. The specification mistakes guide names the scope errors buyers make most often, and the security doors specification guide puts the scope into the order from the start.
Check the installed barrier against its tested foundation
A vehicle barrier rating covers barrier, foundation and ground as one. The post does not stop the vehicle, the foundation does, so a barrier fitted on a different foundation from the one in the test has no rating to show. At handover, ask for the foundation design and check it against the test report.
PAS 68:2013 was withdrawn on 25 October 2023 and superseded by ISO 22343-1:2023, so a barrier ordered today should carry an ISO 22343 rating, and an older PAS 68 rating should be checked against its test report. The ISO 22343 guide reads a rating code field by field, and the bollard foundations guide explains what the rating covers below the pavement.
Check the line as a whole, not one bollard. The gaps between units, the spacing, and the fixings at each end all form part of the tested arrangement. A line with a gap wider than the tested spacing is an open line. The Secured by Design listing guide runs the same check for a scheme listing: the entry is the proof, not the claim.
The as-built record the buyer keeps
The as-built record is the record of what was actually fitted, not what was ordered. It should name each door and each barrier, the size and hardware fitted, the fixings used, the gaps at the leaf, and the wall the frame bolts into. A record made on the day can be used by the next person.
Photograph each opening as fitted, and file the photographs with the record. Note the date and the person who checked it. Where the install differs from the order, write the difference down and the reason for it.
| Check | What to ask for | What a pass looks like |
|---|---|---|
| Installer | LPCB listing for the service | Live entry on Red Book Live |
| Install proof | Certificate of Conformity | Site, product and scope all named |
| Door scope | Certificate and test report | Size, hardware and fixings all inside scope |
| Barrier base | Foundation design and test report | Matches the tested build |
| As-built | Record and photographs | Each opening named as fitted |
| Thread | Golden thread handover | Receipt confirmed in a usable format |
The as-built record also feeds the maintenance that follows. A closer adjusted by hand, a seal worn thin, or a lock swapped for a different model all move the doorset away from its tested build. The Gateway 2 guide explains the same discipline for fire doors in higher-risk buildings.
What the golden thread asks for at handover
For a higher-risk building, the handover has a legal shape. A building counts as higher-risk when it has at least seven storeys or stands at least 18 metres high, and holds at least two homes, or when it is a hospital or a care home. Once the building work ends, the client must seek a completion certificate. To do so, the client must show that the building information has passed to the principal accountable person, the accountable person, or the Responsible Person for a non-residential building.
The handover list covers the information behind the building control application, the information behind the completion certificate application, the completion certificate itself, access to and control of the building information, plus the fire safety information the Responsible Person needs. Whoever receives it must confirm receipt, and confirm that the format is one they can use.
The record is kept in digital form, guarded against unauthorised access, ready when someone needs it, and treated as the building’s single source of truth. The gov.uk golden thread guidance sets out the full list, and the golden thread records guide shows the fire door records that matter inside it. The public frameworks guide shows how the order that led to this handover was placed.
Handover is not a handshake. It is the day the evidence is checked against the building.
When the install does not match the evidence
Do not sign a handover that does not match. A door fitted with untested hardware in the leaf, or a leaf cut down to fit a frame that moved, or a barrier on a foundation the test never saw are all the same problem: the rating no longer matches what is on site. Record the mismatch on the day, with photographs and measurements.
Do not fix it on the day. Swapping the closer, changing the lock, or cutting the leaf down all break the tested construction. Get the evidence before the change is made, not after, and wait until it arrives before the work goes ahead.
No rating can be gained once the doorset is in place. Stronger locks on an untested door do not make a rated doorset, because that combination was never put through a test. The LPCB Red Book sets out how installer schemes work, and the guide to mixing standards in one tender shows the schedule mistakes that make handover fail.
Who issues a Certificate of Conformity?
The installer issues one for each installation, under the LPCB installer scheme structure. It names the site and the product as fitted.
The installed door is a different size from the certificate. What then?
A size outside the scope has no rating to show. Swap the door, or get fresh evidence that covers the door as fitted.
Does the golden thread apply to every building?
No. It applies to higher-risk buildings only: tall residential buildings, hospitals and care homes.
Can a PAS 68 barrier sit on a different foundation from the test?
No. Barrier, foundation and ground are rated as one.
What should the buyer do with a failed check?
Record it on the day, with photographs and measurements, and do not sign. Ask for fresh evidence or a replacement.
Contact us for a free quote
Related
More in guides for specifiers