Commissioning, Handover and the O&M Manual for Security Doors and HVM
From first run to final sign-off: what commissioning proves, what handover hands over, and what the O&M manual must hold for security doors and barriers.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
A door is fitted in a day. Proving it takes longer: every unit run through its movement, every result written down, every paper checked against the building. This guide covers the three steps that close a job, commissioning, handover and the operation and maintenance manual, and the record that follows them.
- CommissioningEvery unit run and recorded
- HandoverThe evidence checked, not assumed
- O&M manualHow the package is run and kept
- Golden threadThe record for the life of the building
What commissioning has to prove
The certificate proves the design. The site proves the fitting. Commissioning sits between them: each unit worked through its full range, each lock tried, each control used as the building will use it. A leaf nobody has opened and shut under its own power is an unproven leaf.
Test the bad day too. Power off at the board, alarm sounding, escape route in use. A leaf that must release on alarm has to release when the alarm sounds, not when the drawing says it should. A barrier that must rise on its own power has to rise when the mains are down.
LPS 1175 Issue 8.2 (September 2024) tests the doorset as one assembly, leaf, frame, hardware, glazing and louvres together, and each opening layout on its own. The maker’s fixing method is assessed with it. What commissioning checks, unit by unit, is whether what stands on site is what passed the test. The test report guide reads the evidence behind a door, figure by figure.
Testing each unit, not just the package
A package result hides a weak unit. Run each leaf, each closer, each barrier on its own, and write each result against the unit it belongs to. A fault found this way points at one leaf; a fault found later points at the whole job.
Powered leaves carry their own checks. On power loss the leaf must reach its safe state, and the hand control must work with a closed fist. Electrically powered locks must release on alarm, on loss of power, on system error, or on override from the escape side. Check each one at the leaf, not at the drawing.
Where fire and security share one leaf, both jobs need proof. The leaf must shut and latch as a fire door and hold its rating as a security door, with the gap around it inside the limit and the closer proved at full opening and again at about 15 degrees. The keeping the rating valid guide gives the routine that holds a door inside its rating.
The record commissioning leaves behind
Without a written record, commissioning is a memory. The record names the unit, the test, the result, the date and the person who ran it. A unit that failed and was fixed shows the fault, the fix and the re-test, so nobody has to take anyone’s word for it.
The record also names what is still open. A foundation still curing, ironmongery still to arrive, a control awaiting a software change: each one goes in with the date it closes. A gap with no date attached follows the job into handover.
The record stays with the building. The programming guide orders the stages from survey to handover, commissioning among them, and the acceptance and snagging guide lists the checks that come before sign-off.
What handover hands over
Handover is the day the papers are matched to the building. Five papers change hands: the certificate for the rating, the listing check, the fitting note, the commissioning note and the maintenance note. Where any one is missing, the sign-off waits.
Each paper answers its own question. The certificate names the rating tested. The listing check shows the listing was live at order. The fitting note shows the tested fixing method was used. The commissioning note shows each unit was run. The installation handover guide puts the buyer’s checks in order, opening by opening.
In a higher-risk building the file is wider. The client hands the Responsible Person the fire safety information, the completion certificate, and the information used for building control approval and for the completion certificate application, with access and control of the building information itself. Whoever receives it confirms it arrived in a usable form. The gov.uk golden thread guidance names what changes hands at completion.
What the O&M manual must hold
The manual is the book the building runs by. It tells the next operator how each leaf opens, locks and releases, how each barrier rises and falls, what each control does, and what happens when the power fails. Products named without their operation leave the operator to guess.
It also carries the upkeep: visits, parts, checks and the record of each one. The NPSA project cycle has three stages, and the last one, operate, is where servicing at set intervals keeps the barrier working. A barrier left unserviced can fail unseen until the day it is needed. The maintenance contract guide sets out the visits, parts and record a contract should name.
The evidence belongs in the manual too: certificates, listing checks and the commissioning record, so the rating can still be proved years after the fitters have gone. Certification is ongoing: the body tests the range, visits the factory, takes products for re-testing through the year, and expects the maker to upgrade products when the standard changes. The in-service care guide covers the routine for a barrier in use.
The record after handover
The record does not end at handover. The golden thread keeps the building’s information where the next person can reach it: stored digitally, held secure, open to those who need it, and written in plain English. Client, principal designer and principal contractor each keep their part current through design and construction; the accountable person keeps it once people live there.
The record must show how the building meets the building regulations and how the work was managed, with version control so changes can be seen. The building control approval file alone holds drawings, a competence declaration, a construction control plan, a change control plan and log, a building regulations compliance statement, a fire and emergency file, client authorisation, a site location plan, a mandatory occurrence reporting plan, a planning statement and a partial completion strategy.
Repairs and changes join the same file. A repair goes to a competent contractor, done promptly, and the work is written into the door’s record. The golden thread guide covers the record the client keeps from design to handover, and the lead times guide puts dates on survey, manufacture and fitting.
When handover is refused
Do not sign a handover the papers do not support. A certificate naming another configuration, a listing that has lapsed, a commissioning record with gaps, a manual without a maintenance schedule: any one of these holds the sign-off. Installer, certificate and as-built record must agree, opening by opening.
A refused handover is a list with dates, not a failed job. The sign-off follows when the items close. NPSA warns that a build done badly can leave a weak point nobody sees until it matters, and that servicing at set intervals catches a fault while it is still small. The NPSA hostile vehicle mitigation guidance covers the project cycle, design, build and operate.
Ask for the missing pieces in writing: when each paper arrives, when each failed unit is re-tested, when the manual is whole. The access guide gives the opening force and clear width checks a rated door must also pass, and the Gateway 2 guide explains the approval a higher-risk building waits for before work starts.
| Test | What it proves | What the record shows |
|---|---|---|
| Full movement | Each unit opens, closes and locks | Unit, result, date, tester |
| Power failure | Manual release and safe state | Release worked, lock state noted |
| Alarm test | Hold-open devices release | Each device, each result |
| Fire close | Leaf closes, latches and seals | Gap, closer test, result |
| Access control | Right people through, wrong kept out | Each credential, each outcome |
A package that has never been run has never been proved. The certificate says what was tested in the laboratory; commissioning says what works on site.
What does commissioning prove that a certificate does not?
The certificate proves the design passed its test. Commissioning proves the units fitted on site move, lock, release and fail safe, each one run and written down.
What papers should handover include?
The rating certificate, the listing result, the fitting and commissioning notes and the maintenance note, with the O&M manual and, for a higher-risk building, the golden thread information.
What must the O&M manual hold?
How each unit is worked, what to do when the power fails, the maintenance visits and checks, and the test evidence behind the rating.
Who keeps the record after handover?
The accountable person keeps the golden thread once the building is occupied, and the record stays digital, secure, available and in plain English.
When should a buyer refuse handover?
When the certificate, the listing, the commissioning record or the manual does not match what stands on site. Hold the sign-off until each item closes with a date.
Contact us for a free quote
Related
More in guides for specifiers
Products
One supplier for the whole building envelope
Ready to specify your project?
Free assessment, written specification and test evidence. Reply within one working day.