PAS 68 Bollard Foundations Explained
A PAS 68 rating belongs to the bollard on its tested foundation. Deep and shallow foundations, ground surveys and utilities, and the evidence to ask for.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
A PAS 68 bollard stops a vehicle because of what sits below the ground, not because of the steel post above it. The post is the part a driver sees, but the impact load travels down the post and into the foundation, and the foundation is what holds the line. A rating that names a vehicle mass, a speed and a penetration distance is a rating for the bollard on its tested foundation, in tested ground. Change the foundation, and the rating no longer describes the installation in front of you.
That is the fact to hold onto through every decision that follows. The choice between a deep foundation and a shallow one, the ground survey, the utilities survey and the foundation drawing all serve one purpose: to put the tested foundation under the tested bollard, in ground that behaves like the ground in the test. The sections below work through each of those decisions in turn, and name the evidence to ask for before the order is placed.
- Rating covers the installationA PAS 68 rating belongs to the tested bollard on its tested foundation, not to the post alone.
- 1,200 mmMaximum clear gap between bollards, measured at 600 mm high.
- ISO 22343-1:2023Current international standard, superseding PAS 68 and IWA 14-1.
- Survey before diggingUtilities and ground conditions decide the foundation type before the design is fixed.
The foundation does the stopping, not the post
When a vehicle strikes a bollard, the post bends and the load moves down into the foundation. The foundation resists by mass and by grip on the surrounding ground. A post set in a shallow socket or a weak slab can be pulled out or pushed over, and the vehicle keeps moving. The test measures penetration: how far the load carrying part travels past the barrier line. A rating of 0 metres penetration means the foundation held the line. A rating with metres of penetration means the vehicle carried on past it.
The size of the foundation follows the threat, not the post. A bollard rated to stop a 7,500 kg truck at 48 km/h needs a foundation that can absorb that energy, and a bollard rated for a 1,500 kg car at the same speed needs less. Two bollards that look the same above ground can need very different foundations below it, and a quote that prices the post without the foundation is not a quote for a rated line.
The same logic applies to the line as a whole. A line fails at its weakest foundation, so every bollard in the line needs the same tested foundation, not just the ones in easy ground. Spacing matters too: the maximum clear gap between bollards is 1,200 mm, measured at 600 mm high, so the line must be set out as a line, with each foundation in its measured place. For the spacing rule and how it is measured, see the PAS 68 bollards guide and the bollard regulations guide.
What the rating covers: bollard, foundation and ground together
A PAS 68 rating is a short code for one crash test. Take V/7500[N3]/80/90:0/0: V means the test used a real vehicle, 7500 is the vehicle mass in kilograms, [N3] is the vehicle category, 80 is the impact speed in kilometres per hour, 90 is the impact angle in degrees, and the figures after the colon are the penetration distance and the debris dispersion distance, both 0 metres. The PAS 68 bollards guide works through the code in full, and the vehicle impact ratings page sets out what a rating must state.
The test installs the bollard in a foundation built to the specification of the product, in ground of a stated type, and the rating records what happened. The foundation drawing is part of the test record: its depth, its plan size, its concrete, its reinforcement or frame, and how the bollard is fixed to it. A rating that does not name its foundation has not been read properly, because the foundation is part of what was tested.
ISO 22343-1:2023 is the current international standard, and it supersedes PAS 68:2013 and IWA 14-1:2013. For a new specification, name ISO 22343-1:2023 and accept a PAS 68 or IWA 14-1 rating only where the project brief still calls for it. The three documents test the same kinds of vehicle: a 1,500 kg car, a 2,500 kg 4×4, a 3,500 kg van, a 7,200 or 7,500 kg truck, and a 30,000 kg truck, at common speeds of 48, 64 and 80 km/h. The guide to PAS 68, IWA 14-1 and ISO 22343 compares the three documents, and the ISO 22343 guide explains the current standard.
What the rating does not cover is just as important. A bollard rated for a 1,500 kg car at 48 km/h has not been shown to stop a 7,500 kg truck at 80 km/h. A bollard tested on a deep foundation has not been shown to work on a shallow one. And a bollard tested in firm ground has not been shown to work in made ground or soft clay. The rating describes one tested installation, and the installation on site must match it.
Deep foundations: how a concrete block spreads the load
A deep foundation is a large block of concrete below ground, with the bollard set into it. When the vehicle strikes, the impact load spreads through the block into the ground around it over a large area, so the ground takes the force without the bollard moving. The block is the anchor, and the post is the lever that carries the load down to it.
Deep foundations suit open ground where digging is straightforward: car park edges, building fronts on clear ground, and sites with no services below. They need excavation, formwork, concrete and curing time, and the ground must take the excavation without shoring or dewatering problems. Where the ground is firm and the services are clear, a deep foundation is the simplest answer.
The depth and size are set by the tested design, not by rule of thumb. The foundation drawing states the depth, the plan size, the concrete specification and the fixing detail, and the installer builds to that drawing. A deeper foundation than the tested one is not automatically better: it changes the installation the test describes, so build to the drawing, not beyond it.
Deep foundations also need the ground around them to be sound. Made ground, soft clay or a high water table change how the block behaves, and a foundation designed for firm ground may fail in soft ground. That is why the ground survey comes before the design is fixed, and why the design must state the ground it assumes. For how the foundation type is matched to the site, see the guide to choosing HVM bollards.
Shallow foundations: a wider raft where depth is limited
A shallow foundation spreads the load across a wider area near the surface, using a steel frame or a raft cast into a shallow concrete pad. The bollards in a line are often linked by the frame, so the impact load is shared across several units instead of falling on one. The load still reaches the ground, but through area rather than through depth.
Shallow foundations suit sites where deep digging is impossible: a basement roof or suspended slab below, dense utilities, listed paving that cannot be disturbed, or ground with a high water table. They also suit sites where the line must be built fast, because less excavation means less disruption to the building and to the people using it.
The trade-off is footprint. A shallow foundation takes up more area at the surface than a deep one, and the frame must be protected from damage during the rest of the works. The surface above it must be reinstated to the same standard as the rest of the site, because a frame left exposed or a pad left unfinished is a trip hazard and a weak point in the line.
A shallow foundation is not a weak foundation. Tested shallow systems stop the same vehicles as tested deep ones, at the same speeds, with the same penetration figures. The difference is how the load is spread, not how much load the line can take. The rating still applies only to the tested unit on its tested foundation: a shallow foundation that was not tested with the bollard carries no rating, however shallow the dig. For the bollard types that use shallow foundations, see the guide to choosing HVM bollards and the security bollards page.
The ground survey: what to find out before the design is fixed
The ground survey answers one question: does the ground on site behave like the ground in the test? A trial pit or a borehole along the line shows the soil, the made ground, the water table and anything buried that the drawings miss. Without it, the foundation design is a guess about ground nobody has seen.
Made ground is the most common surprise. Fill laid over the original soil, often mixed with rubble, behaves differently from firm ground, and a foundation designed for firm ground may fail in it. Soft clay, a high water table, tree roots and existing slabs all change the foundation design in the same way, and each of them is cheaper to find before the order than after the concrete is poured.
Survey points along the whole line give a truer picture than a single pit, because ground conditions change across a site. A line that crosses made ground at one end and firm ground at the other needs a design that answers both, and that answer can only come from survey points that cover the line.
Raise what the survey finds before ordering. If the ground differs from the test ground, the foundation design may need to change, and that change needs agreement in writing before the order is placed. Moving the line is cheap before the order. Moving it after the concrete is poured is not. For the wider survey and testing services that support a specification, see the hostile vehicle mitigation page.
Utilities: mapping what sits at foundation depth
Power cables, gas pipes, water mains, drainage and telecoms ducts all sit at foundation depth, and striking one stops the work and can be dangerous. A utilities survey should map every service along the line before any design is fixed, and the line should move around services where possible.
Where the line cannot move, the service may need to be diverted, and that work needs its own consent and its own programme. A diversion discovered after the order adds delay and cost that a survey would have caught, and it can hold up the whole line while one service is moved.
A shallow foundation disturbs less ground, so it is more likely to sit above services than a deep one. That is one reason shallow systems are chosen on service-heavy ground. But the survey still comes first, because a shallow foundation can still strike a shallow service, and a service that runs across the line at any depth is a service that must be mapped.
Record the survey. The utility drawings, the survey report and any diversion agreements belong with the foundation design in the handover pack, so the next person to dig along the line knows what is below.
What a foundation design must state
A foundation design is a drawing plus a specification, and it must state everything the installer needs to build the tested foundation: the depth, the plan size, the concrete specification, the reinforcement or steel frame, the fixing detail for the bollard, the drainage falls and the finished levels.
It must also state the ground it assumes: the soil type, the bearing conditions and the water table the design was checked against. If the survey shows different ground, the design must be revisited, not built as drawn. A design that assumes firm ground and meets soft clay is a design that was never checked against the site.
Ask for the design in writing before the order, with the test evidence that covers it. The test report or certificate should name the foundation it was tested with, and the drawing should match that foundation. A quote without a foundation detail, a depth and a concrete specification is a quote for a post, not for a rated line. Compare quotes on the same scope: same rating, same foundation, same number of units, same survey and same reinstatement.
The design must also cover the line, not just one bollard: the spacing between units, the edge distances, the joints between foundations where the frame is continuous, and the reinstatement of the surface above. The maximum clear gap between bollards is 1,200 mm, measured at 600 mm high, and the same limit applies at gates, drains and corners, because a vehicle uses the widest gap, not the average gap. For the spacing rule in full, see the bollard regulations guide.
| Question | Deep foundation | Shallow foundation |
|---|---|---|
| How the load spreads | Through a large concrete block into the ground below | Across a wider area near the surface, through a steel frame or raft |
| Depth below ground | Deep excavation, set by the tested design | Shallow excavation, set by the tested design |
| Where it suits | Open ground with straightforward digging | Basement roofs, dense utilities, listed paving, high water table |
| What limits it | Services, water table, shoring, curing time | Surface footprint, protection of the frame during works |
| Evidence to ask for | Foundation drawing and test report naming the deep foundation | Foundation drawing and test report naming the shallow foundation |
The test that proves the foundation, not just the bollard
A bollard rating covers the bollard, the foundation and the ground together, and a test that proves the post on one foundation does not prove it on another. The rating example V/7500[N3]/80/90:0/0 names the vehicle, the mass, the speed, the angle and the penetration, and the foundation that held the vehicle in that test is part of the rating. A bollard fitted on a different foundation has no proven rating, whatever the post itself can do.
ISO 22343-1:2023 is the current vehicle barrier test standard, and it supersedes PAS 68:2013 and cancels and replaces IWA 14-1:2013. Test vehicles run from a 1,500 kg car to a 30,000 kg truck, and test speeds are 48, 64 and 80 km per hour. Ask for the test report naming the bollard, the foundation and the ground, and file it with the design before the order is placed.
The foundation design must state the depth, the size, the concrete and the reinforcement, and the ground the design assumes. A design that names the bollard and leaves the ground to chance is a design that has not been finished. Our PAS 68 bollards guide works through the rating and what it asks of the whole line, and our ISO 22343 vehicle security barriers guide reads the rating field by field.
When the ground will not take the load: what changes
Some sites will not take a deep foundation. A shallow foundation spreads the load over a wider raft where depth is limited, and the raft must be sized for the vehicle the rating names, not for the vehicle the site expects. A raft that suits a car will not stop a truck, and a foundation designed for the wrong vehicle is a foundation that has failed before it is built.
Utilities decide what can be built as much as the ground does. Pipes, cables and drains sit at foundation depth, and a foundation that cuts through them is a foundation that cannot be built. Map what sits below the line before the design is fixed, and move the line or the foundation where the two clash. A survey that finds a pipe after the concrete is poured is a survey that came too late.
ProtectUK guidance sets 1,200 mm as the maximum clear gap between barriers in a line and 500 mm as the minimum height, so check the whole frontage, not only the bollard. A gap wider than 1,200 mm lets a vehicle through between two rated posts, and a line with a gap in it has no rating at all. Our choosing HVM bollards guide works through the line as one system, and our bollard regulations guide sets out what the rules ask of a bollard line.
| Item | What the design must state | Why it matters |
|---|---|---|
| Depth and size | Depth, size, concrete, reinforcement | The rating depends on the foundation |
| Ground | Ground type and bearing the design assumes | A different ground changes the result |
| Utilities | Pipes, cables and drains at foundation depth | A clash stops the build |
| Test evidence | Test report naming bollard, foundation and ground | A post alone has no proven rating |
Order the foundation with the bollard, and file the design, the survey and the test report together, so the next specifier can see what the rating rests on.
What goes wrong when the foundation is specified apart from the bollard
The most common failure is ordering the bollard and the foundation from different decisions: a rated post on a foundation nobody checked. The post arrives tested, the foundation is built to a guess, and the line has no rating. The fix is to specify them together, in one order, against one foundation drawing.
The second failure is changing the depth on site. A deep foundation shortened to miss a cable, or a shallow frame cut to fit around a drain, is no longer the tested foundation. Any change to depth, size or fixing needs agreement before the concrete is poured, not after it has set.
The third failure is building in ground the survey never saw: a void below, made ground, or a water table higher than the design assumed. The foundation settles or moves, the bollard leans, and the line loses the alignment the rating assumed. A line that leans is a line whose spacing no longer measures 1,200 mm at 600 mm high.
The fourth failure is forgetting the surface. Drainage that lets water sit around the base, paving that traps water against the post, or a finish that hides the fixing all attack the fixing first, and a fixing that fails leaves the post standing on nothing. Automatic bollards carry the same risk in a different form: the pit below a rising bollard needs drainage and a level base, as the rising bollards page shows, and a pit that floods is a bollard that stops working.
The fix for all four is the same: one specification, one drawing, one test record, covering bollard and foundation together, checked against the survey before the order is placed. Where the line meets a gate or a barrier, the same discipline applies: the anti-ram gates and barriers guide and the HVM planters and street furniture guide show how the rest of the line is specified. Where the wider duties apply, the Martyn’s Law guide and the transport hub security requirements guide set out what premises must consider.
The rating is for the bollard on its foundation, not for the bollard on its own. A foundation that was never tested carries no rating, however strong the post looks.
Can I fit a PAS 68 bollard into my existing foundation?
Only if that foundation matches the tested foundation for that bollard. A rating belongs to the tested installation, foundation included, so a tested bollard in an untested foundation has no rating. Ask for the foundation drawing and check it against the site before you order.
How deep does a PAS 68 foundation need to be?
There is no single depth. The depth is the one in the tested design for that product, and deep and shallow foundations both work when they are tested. Ask for the foundation drawing and the test report that names it, and build to the drawing.
What if the ground on site differs from the test ground?
Raise it before ordering. The foundation design may need to change, and that change needs agreement in writing before the order is placed. A trial pit or a borehole along the line answers the question early, when moving the line is still cheap.
Do shallow foundations stop the same vehicles as deep ones?
Yes, when they are tested. The rating states the vehicle, the speed and the penetration, and the foundation type does not change what the rating proves. A shallow foundation that was not tested with the bollard carries no rating, just as an untested deep one does not.
What should I ask for in a bollard foundation quote?
The full rating code, the foundation drawing and depth, the concrete and frame specification, the survey scope and the reinstatement included. Compare quotes on the same scope, and ask for the test evidence to be supplied with the installation.
Get a free quote
Related
More in guides for specifiers
Products
One supplier for the whole building envelope
Ready to specify your project?
Free assessment, written specification and test evidence. Reply within one working day.