Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets
Regulation 38 says the person carrying out the work must give fire safety information to the responsible person. This guide sets out what the pack holds.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
A fire-rated security doorset is only as useful as the information handed over with it. The person carrying out the work hands that information to the responsible person at completion, or at first occupation if that comes first.
- Regulation 38The duty at handover
- Responsible personReceives the information
- TimingCompletion or first occupation
- DoorsetRating and evidence
What Regulation 38 asks for
Regulation 38 applies where building work erects or extends a relevant building, or is carried out in connection with a relevant change of use, and Part B of Schedule 1 imposes a requirement in relation to the work. A relevant building is one where the Regulatory Reform (Fire Safety) Order 2005 already applies, or will apply once the work is finished.
Fire safety information means information relating to the design and construction of the building or extension, and the services, fittings and equipment provided in or in connection with it, which will assist the responsible person to operate and maintain it with reasonable safety. The definition sits in regulation 38(3), and Approved Document B Volume 2 gives guidance on what the information should contain.
The aim is practical. Approved Document B says the aim of the regulation is to ensure the person responsible for the building has sufficient information to manage it effectively, and that the aim is met when that person has all the information to understand and implement the fire safety strategy, maintain any fire safety system, and carry out an effective fire risk assessment.
Who gives it and who receives it
The duty sits with the person carrying out the work. That person must give the fire safety information to the responsible person, who has the meaning given by article 3 of the Regulatory Reform (Fire Safety) Order 2005. Approved Document B says the information should be given to the relevant dutyholder, the responsible person or the accountable person.
The person carrying out the work is the one who holds the information. The design, the as-built record and the test evidence sit with the firms that built and fitted the work, so the handover must collect them before the site clears. The commissioning and handover guide lists what papers a door should carry.
The golden thread carries the record forward. A higher-risk building keeps a wider file, and the Regulation 38 information forms its opening entries. The golden thread guide names the digital record and who keeps it.
When it must be given
Where the building or extension is not occupied during the work, the information must be given by the date of completion or the date of occupation, whichever is the earlier. Where the building is occupied during the work, the deadline is the date of completion. Approved Document B gives the same two points.
Occupation before completion moves the deadline forward. A building occupied before the work is finished still needs the information by the date of occupation, not by the later completion date. The replacement guide deals with a door swapped while the building stays in use, and the handover date needs the same care.
The installation handover guide checks each opening in turn.
The acknowledgement and the notice to building control
The responsible person must give the person carrying out the work a notice acknowledging receipt of the fire safety information and confirming the information is sufficient to enable them to understand, operate and maintain the building, and the fire safety systems in it, after the work. The notice is part of the duty, not a courtesy.
The person carrying out the work must then give a notice to the relevant authority confirming the information was given, and stating that the responsible person’s notice was received, or where it was not received, the steps taken to obtain it and the dates they were taken. The notification must be given no later than five days after the handover date, or 30 days where regulation 20 applies.
A third-party certification route has its own timing. Where regulation 20A applies, the third-party certifier must be notified within seven days, and the certifier must notify the relevant authority within 30 days of receiving that notification. The fire door regulations guide notes the Regulation 38 handover at the same point in its own checklist.
What goes in the pack for a fire-rated doorset
Approved Document B says the essential information should let the relevant dutyholder understand, operate and maintain the building, including the fire safety systems in it, and should make clear how the fire safety arrangements are intended to operate together. Where a fire safety strategy has been prepared, it should be made available to the relevant dutyholder.
An as-built plan should be provided showing the escape routes with exit capacity, the fire-resisting construction and the location of fire-separating elements including cavity barriers in walk-in spaces, and the fire doorsets, including fire doorsets fitted with a self-closing device and other doors relevant to the fire safety strategy, such as doors equipped with relevant hardware. The plan should also show detector heads, manual call points, alarm control and indicating equipment, sounders, signage, emergency lighting, extinguishers, fire mains, hydrants, sprinklers, smoke control systems, high-risk areas, power supplies and secure information boxes.
Details should also be provided of the specifications of fire safety equipment, including routine maintenance schedules, any assumptions about the management of the building, and any provision for the evacuation of disabled people. A doorset with no maintenance schedule leaves the responsible person guessing how often the closer, seals and hardware should be checked, so the schedule belongs in the pack. The fire door inspection checklist runs through what the schedule should cover.
What a complex building needs on top
Approved Document B says the guidance on information is not exhaustive, and the level of detail should be considered case by case. For a complex building, a detailed record should be provided of the fire safety strategy and of the procedures for operating and maintaining any fire protection measures, including an outline cause and effect matrix. Further guidance is in clause 9 and Annex H of BS 9999.
The records should include the fire safety strategy with all assumptions in the design, any risk assessments or risk analysis, and all assumptions about the management of the building. They should also cover escape routes with occupant load and capacity, provision for the evacuation of disabled people including evacuation lifts, the escape strategy, assembly points, and passive fire safety measures.
A dual-certified door needs both proofs in the record. One assembly carries a fire proof and a security proof, and the pack should name both. The dual-certified doors guide covers keeping both ratings valid.
What to check before you sign for the doorset
Check the pack against the three aims. The responsible person should be able to follow the fire safety strategy, keep every fire safety system in the building working, and complete an effective fire risk assessment. A pack that leaves any of the three unanswered is not finished.
Check the doorset items one by one. The as-built plan should show the doorset and its self-closing device, the specification should name the fire rating and the test evidence, and the maintenance schedule should set out how often the closer, seals and hardware are checked.
Check that the two files are not confused. The health and safety file under CDM 2015 is for the next construction project, and the Regulation 38 pack is for the person who runs the building. The CDM duties guide sets out who prepares the health and safety file. Planning permission is a third question again, and the planning permission guide walks through the checks.
| Item | Where it sits | What to check |
|---|---|---|
| Fire doorset and hardware | As-built plan, self-closing device named | Rating and evidence match the doorset fitted |
| Escape routes | As-built plan, exit capacity for each storey | Routes and exits match the strategy |
| Fire safety strategy | Essential information | Strategy explains how the arrangements work together |
| Alarm, detection and lighting | As-built plan, detector heads and call points | Locations match the building as built |
| Maintenance schedules | Equipment specifications | Closer, seals and hardware have a check interval |
The pack is judged by whether the responsible person can run the building from it, not by how thick it is.
When does Regulation 38 apply?
Where the work puts up or extends a relevant building, or follows a relevant change of use, and Schedule 1 Part B sets a requirement for the work. The Fire Safety Order applies to the building now, or will apply after the work is done.
Who must give the fire safety information?
The person carrying out the work hands it to the responsible person. Where the building is empty during the work, the date is completion or first occupation, whichever is earlier. Where it is occupied during the work, the date is completion.
Must the responsible person confirm anything?
Yes. The responsible person must give a notice acknowledging receipt and confirming the information lets them understand, operate and maintain the building and its fire safety systems.
How quickly must building control be told?
The person carrying out the work sends the notice to the relevant authority within five days of the handover date. Where a self-certification scheme under regulation 20 applies, the limit is 30 days. Under a third-party scheme, the certifier is notified within seven days and must notify the authority within 30 days.
What should the pack say about a fire-rated doorset?
The plan should show the doorset and any self-closing device, the specification should carry the rating with its test evidence, and the schedule should give a check interval for the closer, seals and hardware.
Contact us for a free quote
Related
More in guides for specifiers
Products
One supplier for the whole building envelope
Ready to specify your project?
Free assessment, written specification and test evidence. Reply within one working day.