An LPS 1175 rating covers the tested assembly. This UK guide explains the changes that void it, the inspection routine to follow, and the records to keep.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

An LPS 1175 rating belongs to the tested assembly, not to the door alone. It stays valid while the doorset matches the tested build and is maintained to a schedule. New locks, drilled holes, replaced glazing or wall alterations can void it. This guide sets out the inspection routine and the records to keep.

  • The ratingApplies to the tested assembly: leaf, frame, locks, glazing and fixings together.
  • What voids itUnapproved changes: new locks, drilled holes, replaced glazing, altered walls.
  • InspectionA short routine, monthly to annually, checking operation, fixings, seals and glazing.
  • RecordsKeep the test evidence, the installation record and every maintenance visit on file.

What the rating actually covers

LPS 1175 tests the product as a complete assembly. The rating on the doorset covers the leaf, the frame, the locks, the glazing and the fixings working together, installed the way the manufacturer describes. It does not rate the lock on its own, the glass on its own, or a leaf hung in a different frame. Change any part of that assembly and the rating no longer describes what is on the wall. Our LPS 1175 guide explains how the ratings are earned.

This is why the paperwork matters as much as the steel. The test evidence names the exact build that passed. Your job after installation is to keep the doorset matching that build, and to prove it with records. Everything in this guide follows from that one idea, and the same thinking appears in our guides on related ratings.

The rating also stays with the doorset, not the building. If a rated door is removed and refitted elsewhere, the reinstallation must follow the manufacturer’s method and the new wall must suit the rating, or the evidence no longer describes the installation. Relocation is a new installation in the eyes of the rating, and it needs the same care as the first fit. Our security doors are supplied with the installation detail the rating assumes.

Changes that void the rating

Some changes obviously break the rating. Fitting a different lock, drilling new holes for cables or signage, swapping the glazing for a different make-up, or cutting the leaf down all change the tested assembly. The rating cannot survive changes the test never saw, because the test is the only proof the rating has.

Wall alterations count too. The test assumes the surrounding structure resists attack at least as well as the doorset. If a refurbishment replaces a masonry wall with a lightweight partition beside the door, the weak point moves and the rating becomes meaningless. Any building work near a rated doorset should be checked against the original specification first. On busy estates such as schools, minor works happen often, so the facilities team needs to know which doors are rated; our education sector page shows where these doorsets usually sit.

Electronic hardware deserves the same caution. Adding a maglock, a strike or a cable route means drilling, new fixings and new loads on the leaf and frame. Access control should be part of the original specification wherever possible. Retrofitting it to a rated doorset needs the installer’s written approval before anyone picks up a drill. If the work is planned, involve the installation team early so the method can be agreed in writing.

Even small additions need care: door closers, viewers, kick plates and signage fixed with screws all pierce or load the leaf. If the tested build did not include them, ask the installer before fitting them. The safe rule is simple: if it was not in the tested assembly, do not add it without written advice.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

A simple inspection routine

A short routine catches most problems before they matter. The table below suits a typical commercial doorset, from SR2 doors upward. Adjust the frequency to the site, with busier doors and harsher exposures checked more often. The person doing the checks needs no specialist tools, only the schedule and a way to record what they find.

Check What to look for Frequency
Operation Door opens, closes and latches without force Monthly
Locks All locking points engage fully; cylinders turn smoothly Monthly
Hinges and fixings No loose screws, no dropped leaf, no play in the frame Quarterly
Seals Weather and smoke seals intact, seated and uncut Quarterly
Glazing Beads secure, no cracked panes, no loose gaskets Quarterly
Frame and wall No cracks, no gaps at the frame edge, fixings tight Annually
Finish No deep corrosion, coating sound Annually

Write each check down with the date and the result. A tick sheet kept on file turns maintenance from a chore into evidence, and evidence is what an insurer or auditor asks for after an incident. Our maintenance service, done by our own team or by our installation partners, follows this routine and returns the records with every visit.

Doors that carry both a fire and a security rating need checks for both. Our fire door inspection checklist covers the fire side of that routine, from seals to closers.

Lubrication, seals and finishes

Locks and hinges need light lubrication to the manufacturer’s instruction. Use the product the maker names, applied sparingly to moving parts. Never use heavy grease that traps grit, and never oil a cylinder that the maker says should run dry. Stiff operation is a warning: find the cause rather than forcing the door, because force masks the fault and wears the mechanism.

Seals do quiet work and fail quietly. Check weather seals for splits and compression set, and check that smoke seals sit correctly in their grooves. Replace damaged seals with the same type the doorset was tested with. A seal from a different supplier may look identical and perform differently under attack or fire.

Repainting rules are strict on rated doorsets. Do not paint over intumescent seals, smoke seals or identification labels. Mask them before painting, and use a coating the manufacturer approves for the substrate. On combined fire and security doorsets, the wrong paint on the wrong seal can affect both ratings. Our fire and security doors carry both performances, so their finishing instructions deserve particular care.

Records to keep

Keep four sets of paper for every rated doorset: the test evidence for the rating, the installation record showing it was fitted to the manufacturer’s method, the maintenance log with dates and findings, and written approval for any change made after installation. Store them where the facilities team can find them, not in one person’s inbox. If the doorset includes rated glazing, record the class and spall marking too; our guide to bullet resistant vs bulletproof glass explains what those markings mean.

Photographs help. A dated photo of each doorset, showing the leaf, frame, locks and labels, gives the next contractor or auditor a baseline to compare against. Store the photos with the log, and retake them after any change, however small. A picture taken today settles arguments about damage tomorrow.

When a door changes hands between contractors or the building changes owner, the records should travel with it. A rating without paperwork is a claim, and claims do not satisfy insurers. A complete file does. The comparison in our LPS 1175 vs EN 1627 guide makes the same point from the specification side: the rating is only as useful as the paper that proves it.

When to call the installer

Call the installer before any change, not after. New access control, a different cylinder, additional signage, building work beside the door: all of these deserve a written answer first. The installer knows the tested build and can say whether a change is harmless, needs a like-for-like part, or needs a fresh look at the specification. A quick question now beats a voided rating later.

Call urgently if the door has been attacked, forced, or hit by a vehicle, even if it still works. Hidden damage to fixings or the frame can leave the rating intact on paper and gone in practice. After any incident, the doorset needs inspection, the log needs an entry, and the insurer needs to know.

Drill nothing without advice. A single new hole for a cable or a sign can void the rating on the whole doorset. Ask the installer first; the answer is usually quick.

What the rating does not cover after handover

The rating covers the doorset as supplied and installed, not as it becomes. It does not cover a wall that is rebuilt around the door, a floor that is raised against the threshold, or a corridor that is re-planned so the door opens the other way. Each of those changes the opening the test described, and the rating does not follow the change.

It does not cover use the test never saw. A doorset tested for occasional use, then put on a corridor that cycles hundreds of times a day, wears its hinges, closer and lock faster than the test assumed. The rating is a test result, not a promise about every use, and heavy use needs a heavier inspection routine.

It does not cover damage. A leaf dented by a trolley, a frame bent by a forklift, a lock forced by a lost key, each takes the doorset outside its tested state until it is repaired with the tested parts. A repair with a different lock case, a different hinge or a different seal is a change to the tested assembly, not a repair.

It does not cover the finish. Powder coating that is chipped and left bare lets corrosion start at the breach, and corrosion at a hinge or a fixing weakens the assembly the test relied on. Touch up chips promptly, and treat the finish as part of the rating, not as decoration. The same applies to glazing: a vision panel that is cracked or loose changes the assembly the test described, so check the bead and the seal around the glass at every visit.

And it does not cover time on its own. A rating has no expiry date, but the doorset ages. Seals harden, fixings loosen, the frame moves with the building. The rating stays valid only while the doorset still matches its test evidence, and the inspection routine is what proves that match.

Evidence to keep for the next inspection

Ask for the evidence before the order is placed, not after the doors arrive. The six items below belong in the handover pack, and the next inspection starts from them.

  • The LPS 1175 certificate, naming the standard, the issue, the rating and the exact doorset.
  • The hardware schedule, listing every lock, hinge, closer and seal as tested.
  • The test report, showing the tool category, the attack time and the construction tested.
  • The installation record, showing the fixings, the frame and the wall the door was fitted into.
  • The inspection log, with dates, findings and the name of the person who checked the door.
  • The repair record, showing every part changed and the evidence that the replacement matches the test.

A door with its evidence in order is a door that can be checked, repaired and kept. For the ratings in full, see the LPS 1175 page, and for writing the specification so these decisions are made once, see the guide to specifying security doors. For planned servicing and records, see our maintenance page, and for the fire door side of the same discipline, see the fire door inspection checklist.

Frequently asked questions

Does replacing a lock cylinder void the rating?

Fitting a different cylinder changes the tested assembly, so it can. Always fit the cylinder the rating was tested with, or get written approval from the installer first. Keep the receipt and the product details in the maintenance file.

How often should a rated door be inspected?

Monthly checks of operation and locks suit most commercial doors, with a fuller quarterly look at hinges, seals and glazing, and an annual check of frame, wall and finish. Busier doors and harsher sites deserve shorter intervals.

Can we repaint the door ourselves?

Yes, if you mask the seals and labels and use an approved coating. Never paint intumescent or smoke seals, and never cover the rating label. If in doubt, ask the installer which products are approved for your doorset.

The wall beside the door is being rebuilt. Does that matter?

It can. The rating assumes the surrounding structure resists attack at least as well as the doorset. Tell the installer before the work starts so the new construction can be checked against the original specification.

What if the door was forced during a break-in?

Treat the rating as suspect until the doorset is inspected. Damage to fixings, frame or leaf may not show on the surface. Log the incident, arrange an inspection, and keep both on file for the insurer.

Do we need a specialist maintenance contract?

Not always, but the work must follow the manufacturer’s schedule and be recorded. For high-risk sites and large estates, a contract with the installer keeps the routine consistent and the records complete.

Not sure your doors still match their rating?Send the rating and a few photos through the quote form and we will tell you what to check first.
Get a free quote

Related

More in guides for specifiers

10 mistakes when specifying certified security doors 10 steps to specify an LPS 1175 door Acceptance and Snagging of a Security Door or Barrier Job Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire door regulations for commercial buildings in the UK Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Depots Explained Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Doors and Gateway 2 in Higher-Risk Buildings Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to Specify Fire Doors in a Housing Tender How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Programming a Security Door and Barrier Package on a Live Site Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Server Room Doors Explained Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →

Products

One supplier for the whole building envelope

Ready to specify your project?

Free assessment, written specification and test evidence. Reply within one working day.