Fire Doors and Gateway 2 in Higher-Risk Buildings
Gateway 2 is the hard stop before fire door work starts on a higher-risk building. What counts as higher-risk, what Category A means, and what to show.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
Gateway 2 is the point where the Building Safety Regulator must approve building work on a higher-risk building before it starts, and fire doors sit at the centre of that check, because they are the passive fire protection the escape routes depend on.
- 18 metres or 7 storeysHeight test for a higher-risk building, with 2 residential units
- Gateway 2Building control approval before work starts
- 12 weeks new, 8 weeks existingTime the regulator has to assess an application
- Criminal offenceStarting building work without the required approval
First, check whether the building is higher-risk
A higher-risk building is a building in England that is at least 18 metres high or has at least 7 storeys, and contains at least 2 residential units. Height is measured from the ground level next to the building to the top floor that can be walked on. A hospital or a care home that meets the height test counts as higher-risk for building work too, and the Building Safety Regulator is the building control authority for these buildings.
A block of six storeys and 16 metres is not higher-risk, even with a hundred flats, and its building work is approved by the local authority or a registered building control approver instead. Height is counted from the lowest part of the ground next to the building, and storeys below ground and plant-only rooftop floors do not count.
Gateway 2 is the hard stop before work starts
The regime runs in three stages. Gateway 2 is the building control approval application, and it is a hard stop: no building work can start until the regulator has approved it. Gateway 3 is the completion certificate, and a higher-risk building with at least 2 residential units must be registered before people live there.
The client must make sure approval is granted before any building work starts. Carrying out building work without the required approval is a criminal offence, and the regulator checks that the work will comply with the building regulations and that competent people have been appointed. The government’s building control approval guidance sets out the whole process in full.
| Gateway | Stage | What happens | Fire door point |
|---|---|---|---|
| Gateway 1 | Planning | Fire statement with the planning application | Escape routes and access set out early |
| Gateway 2 | Before work | Building control approval from the regulator | Doorset evidence and fire strategy checked |
| Gateway 3 | Completion | Completion certificate, then registration | As-built doors checked against the approval |
Unless an extension is agreed, the regulator has up to 12 weeks to assess an application for a new higher-risk building and up to 8 weeks for work to an existing one. Our fire door remediation programme guide sets out how a housing provider builds the survey and evidence a Gateway 2 application can draw on.
Fire doors are Category A work
Building work to an existing higher-risk building is classed as Category A or Category B, and applying under the wrong category is likely to see the application rejected. Category A includes changing the external height or width, the number of storeys, the layout inside the building or the number of residential units, work involving passive fire safety measures such as fire-resistant materials, work involving active fire safety measures, work affecting staircases or other escape routes, and work on the common areas or parts, including remediation work.
A fire door is a passive fire safety measure, and it sits in the common parts: flat entrance doors, stair doors, lobby doors and corridor doors. Replacing or upgrading them therefore falls in Category A, and the application must carry the fire and emergency file, often called the fire strategy, with plans showing the escape routes and the fire service access. Our fire door certification guide covers the certificate and test evidence a doorset should show.
A fire door is not a fitting to be swapped on a maintenance round. In a higher-risk building it is part of the fire strategy, and changing it without the approval the law requires can leave the whole building outside the regime.
What the application must show about fire doors
The application must explain how the effect of the work on the building was assessed, what the assessments found, and how the work will comply with the building regulations. For fire doors, that means naming each opening, the rating it must carry, and the evidence behind it. The fire and emergency file should show the doors on the plans, with the compartment lines they protect and the escape routes they serve.
Before applying, the client should complete surveys, inspections or building information checks to evidence any effect the work may have on the building. Assumptions should be avoided, and where one is unavoidable the application must provide evidence from surveys and inspections to explain it. The government’s guidance on preparing the application lists the documents and plans each application needs. Our fire rated steel doors range lists the ratings, sizes and options for each design.
What is exempt, and what is not
Some work needs no building control approval at all. The government’s exempt list covers most repairs, replacements and maintenance work, except heating systems, oil tanks, fuse boxes and glazing units, plus replacing sanitaryware and insulation, and external doors where less than 50 percent of the surface is glazed. Work under a competent person scheme also needs no approval.
That list has two limits a housing provider should know. First, the exempt list covers repairs, replacements and maintenance in general, while the Category A list covers passive fire safety measures and work on common parts, and a fire door is both. Second, exempt or scheme work that forms part of a wider building project must be included in the building control approval application for that project. Our housing tender guide sets out how to write a specification a Gateway 2 application can rely on.
Emergency repairs: notify first, regularise after
An emergency repair is building work carried out to manage an urgent risk to the health, safety or welfare of people in or about the building, where the risk cannot be avoided by temporary management arrangements. It can be carried out promptly without building control approval first, but the regulator must be told about it by the end of the first working day after the repair work starts.
After the work is complete, a regularisation certificate must be applied for as soon as possible. A copy of the emergency repair information must go to the responsible person under the Fire Safety Order. The principal accountable person must update the safety case report to include the emergency repair work, and if the repair managed a risk of fire spread or structural failure, the relevant accountable person must submit a mandatory occurrence notice to the regulator.
After approval: change control, notices and completion
Approval is not the end of the regulator’s involvement: the documents uploaded with the application become the agreed documents, and the work must comply with them throughout the build. Any change to an agreed document is a controlled change, managed under the change control plan. The regulator must be told about any change of client, principal designer or principal contractor, and any notifiable or major change. If a major change is wanted, building work must stop on that part of the project until the regulator gives building control approval for the change.
During the project, a notice of intention to start work must be given at least 5 working days before starting, and a notice of commencement within 5 working days. When the work is complete, a completion certificate must be applied for, and the regulator issues it only if satisfied the work meets the building regulations. Occupation must wait until a higher-risk building holding at least 2 residential units is registered, and a completion certificate is needed to register it. Approval lapses if the work has not reached commencement within 3 years. Our commercial buildings regulations guide sets out the wider duties that sit beside the Gateway 2 process.
Does replacing one fire door need Gateway 2 approval?
The exempt list covers most repairs, replacements and maintenance, but Category A covers passive fire safety measures and common parts work. A fire door falls under both lists. A single like-for-like replacement may be exempt; a programme across a block should be treated as building work.
How long does the regulator take to decide a Gateway 2 application?
Twelve weeks at most for a new higher-risk building, and eight weeks at most for work to an existing one, unless an extension is agreed. No building work can start until the application is approved.
What happens if building work starts without approval?
Carrying out building work without the required building control approval is a criminal offence. Work must not start on any part that is subject to a requirement until the regulator is satisfied it has been met.
Is a fire door replacement an emergency repair?
Only where it manages an urgent risk that cannot be avoided by temporary arrangements. A planned replacement is not an emergency repair.
Does Gateway 2 apply to a block under 18 metres?
No. A building under 18 metres high and under 7 storeys is not a higher-risk building, even if it holds many flats. Its building work is handled by the council or a registered building control approver instead.
Contact us for a free quote
Related
More in guides for specifiers