Fire Doors and Gateway 2 in Higher-Risk Buildings

Gateway 2 is the hard stop before fire door work starts on a higher-risk building. What counts as higher-risk, what Category A means, and what to show.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

Gateway 2 is the point where the Building Safety Regulator must approve building work on a higher-risk building before it starts, and fire doors sit at the centre of that check, because they are the passive fire protection the escape routes depend on.

  • 18 metres or 7 storeysHeight test for a higher-risk building, with 2 residential units
  • Gateway 2Building control approval before work starts
  • 12 weeks new, 8 weeks existingTime the regulator has to assess an application
  • Criminal offenceStarting building work without the required approval

First, check whether the building is higher-risk

A higher-risk building is a building in England that is at least 18 metres high or has at least 7 storeys, and contains at least 2 residential units. Height is measured from the ground level next to the building to the top floor that can be walked on. A hospital or a care home that meets the height test counts as higher-risk for building work too, and the Building Safety Regulator is the building control authority for these buildings.

A block of six storeys and 16 metres is not higher-risk, even with a hundred flats, and its building work is approved by the local authority or a registered building control approver instead. Height is counted from the lowest part of the ground next to the building, and storeys below ground and plant-only rooftop floors do not count.

Gateway 2 is the hard stop before work starts

The regime runs in three stages. Gateway 2 is the building control approval application, and it is a hard stop: no building work can start until the regulator has approved it. Gateway 3 is the completion certificate, and a higher-risk building with at least 2 residential units must be registered before people live there.

The client must make sure approval is granted before any building work starts. Carrying out building work without the required approval is a criminal offence, and the regulator checks that the work will comply with the building regulations and that competent people have been appointed. The government’s building control approval guidance sets out the whole process in full.

Gateway Stage What happens Fire door point
Gateway 1 Planning Fire statement with the planning application Escape routes and access set out early
Gateway 2 Before work Building control approval from the regulator Doorset evidence and fire strategy checked
Gateway 3 Completion Completion certificate, then registration As-built doors checked against the approval

Unless an extension is agreed, the regulator has up to 12 weeks to assess an application for a new higher-risk building and up to 8 weeks for work to an existing one. Our fire door remediation programme guide sets out how a housing provider builds the survey and evidence a Gateway 2 application can draw on.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

Fire doors are Category A work

Building work to an existing higher-risk building is classed as Category A or Category B, and applying under the wrong category is likely to see the application rejected. Category A includes changing the external height or width, the number of storeys, the layout inside the building or the number of residential units, work involving passive fire safety measures such as fire-resistant materials, work involving active fire safety measures, work affecting staircases or other escape routes, and work on the common areas or parts, including remediation work.

A fire door is a passive fire safety measure, and it sits in the common parts: flat entrance doors, stair doors, lobby doors and corridor doors. Replacing or upgrading them therefore falls in Category A, and the application must carry the fire and emergency file, often called the fire strategy, with plans showing the escape routes and the fire service access. Our fire door certification guide covers the certificate and test evidence a doorset should show.

A fire door is not a fitting to be swapped on a maintenance round. In a higher-risk building it is part of the fire strategy, and changing it without the approval the law requires can leave the whole building outside the regime.

What the application must show about fire doors

The application must explain how the effect of the work on the building was assessed, what the assessments found, and how the work will comply with the building regulations. For fire doors, that means naming each opening, the rating it must carry, and the evidence behind it. The fire and emergency file should show the doors on the plans, with the compartment lines they protect and the escape routes they serve.

Before applying, the client should complete surveys, inspections or building information checks to evidence any effect the work may have on the building. Assumptions should be avoided, and where one is unavoidable the application must provide evidence from surveys and inspections to explain it. The government’s guidance on preparing the application lists the documents and plans each application needs. Our fire rated steel doors range lists the ratings, sizes and options for each design.

What is exempt, and what is not

Some work needs no building control approval at all. The government’s exempt list covers most repairs, replacements and maintenance work, except heating systems, oil tanks, fuse boxes and glazing units, plus replacing sanitaryware and insulation, and external doors where less than 50 percent of the surface is glazed. Work under a competent person scheme also needs no approval.

That list has two limits a housing provider should know. First, the exempt list covers repairs, replacements and maintenance in general, while the Category A list covers passive fire safety measures and work on common parts, and a fire door is both. Second, exempt or scheme work that forms part of a wider building project must be included in the building control approval application for that project. Our housing tender guide sets out how to write a specification a Gateway 2 application can rely on.

Emergency repairs: notify first, regularise after

An emergency repair is building work carried out to manage an urgent risk to the health, safety or welfare of people in or about the building, where the risk cannot be avoided by temporary management arrangements. It can be carried out promptly without building control approval first, but the regulator must be told about it by the end of the first working day after the repair work starts.

After the work is complete, a regularisation certificate must be applied for as soon as possible. A copy of the emergency repair information must go to the responsible person under the Fire Safety Order. The principal accountable person must update the safety case report to include the emergency repair work, and if the repair managed a risk of fire spread or structural failure, the relevant accountable person must submit a mandatory occurrence notice to the regulator.

After approval: change control, notices and completion

Approval is not the end of the regulator’s involvement: the documents uploaded with the application become the agreed documents, and the work must comply with them throughout the build. Any change to an agreed document is a controlled change, managed under the change control plan. The regulator must be told about any change of client, principal designer or principal contractor, and any notifiable or major change. If a major change is wanted, building work must stop on that part of the project until the regulator gives building control approval for the change.

During the project, a notice of intention to start work must be given at least 5 working days before starting, and a notice of commencement within 5 working days. When the work is complete, a completion certificate must be applied for, and the regulator issues it only if satisfied the work meets the building regulations. Occupation must wait until a higher-risk building holding at least 2 residential units is registered, and a completion certificate is needed to register it. Approval lapses if the work has not reached commencement within 3 years. Our commercial buildings regulations guide sets out the wider duties that sit beside the Gateway 2 process.

Does replacing one fire door need Gateway 2 approval?

The exempt list covers most repairs, replacements and maintenance, but Category A covers passive fire safety measures and common parts work. A fire door falls under both lists. A single like-for-like replacement may be exempt; a programme across a block should be treated as building work.

How long does the regulator take to decide a Gateway 2 application?

Twelve weeks at most for a new higher-risk building, and eight weeks at most for work to an existing one, unless an extension is agreed. No building work can start until the application is approved.

What happens if building work starts without approval?

Carrying out building work without the required building control approval is a criminal offence. Work must not start on any part that is subject to a requirement until the regulator is satisfied it has been met.

Is a fire door replacement an emergency repair?

Only where it manages an urgent risk that cannot be avoided by temporary arrangements. A planned replacement is not an emergency repair.

Does Gateway 2 apply to a block under 18 metres?

No. A building under 18 metres high and under 7 storeys is not a higher-risk building, even if it holds many flats. Its building work is handled by the council or a registered building control approver instead.

Ready to plan fire door work in a higher-risk building?Send the building height and storeys, the door schedule and the rating for each opening.
Contact us for a free quote

Related

More in guides for specifiers

10 mistakes when specifying certified security doors 10 steps to specify an LPS 1175 door Acceptance and Snagging of a Security Door or Barrier Job Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire door regulations for commercial buildings in the UK Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Depots Explained Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to keep an LPS 1175 door rating valid after installation How to Specify Fire Doors in a Housing Tender How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Programming a Security Door and Barrier Package on a Live Site Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Server Room Doors Explained Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →

Products

One supplier for the whole building envelope

Ready to specify your project?

Free assessment, written specification and test evidence. Reply within one working day.