A depot holds vehicles, fuel and stores behind its yard gate, so each fire door takes its period from the room behind the leaf, workshop to plant room.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

A depot is a yard ringed by workshops, stores and offices, where vehicles come and go through the gate all day and the fire doors are the leaves that keep a fire in the room where it began while the drivers and the fitters find the way out. The period on each door follows the room behind the leaf, because a workshop full of fuel and vehicles asks more of its doors than an office full of paperwork.

Depots share their fire rules with warehouses, and those shared rules are set out in the fire door regulations warehouses guide, while the doors that guard a warehouse yard are covered in the warehouse security doors guide. The depot order names every opening with its period and its hardware beside it, so the leaf that arrives is the leaf the room asked for.

Before a single leaf is ordered the depot writes down its fire plan, giving each opening the period it must hold and each person the route they must follow, and the order is built from that plan door by door.

  • FD30 / FD60Fire periods to EN 1634-1
  • E / EW / EI 30-120What the letters beside the period mean
  • Sa / S200Smoke proof to BS EN 1634-3
  • One listEvery depot door named

Workshops, stores and offices: a depot in three parts

A depot works as three places: the workshops where the vehicles are kept running, the stores where the parts and the fuel sit, and the offices where the jobs are booked and the records are kept. The rules follow those places, because a leaf between a workshop and a stores room must hold the fire on the side where it started while the people on the far side reach the way out.

The workshops take the doors that let vehicles and fitters pass in and out through the day, and each leaf must open for a driver who has never seen the building before. The stores take the doors that guard the stock, and each leaf must hold the fire back where the goods sit on racks and pallets.

The plan gives every opening a door of its own, so a leaf ordered for the office never ends up guarding the workshop, and a leaf ordered for the stores never ends up on the route.

FD30 and FD60 in a depot: which room takes which period

Each part of a depot asks a different period of its doors, because the load behind each leaf differs. The workshops hold vehicles and fuel, the stores hold parts in boxes and on pallets, and the plant room holds the machinery that serves the whole yard, so the period on each door follows the room and never the leaf alone.

In the furnace test to EN 1634-1 the leaf faces flames and heat while the minutes are counted, and the result pairs a number with letters. The number counts the minutes the leaf held, and the letters say whether the flames alone were stopped, the flames with some of the heat, or the flames with the heat as well.

A leaf proved for 60 minutes is heavier than one proved for 30, and the frame must be deeper to carry it, so the figure on the order rises with the period. A 30-minute leaf has no place in an opening that asks for 60, because the shortest proof in the wall is the one that gives way first.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

The workshop: vehicles, fuel and the doors around them

A workshop is a wide room full of vehicles, tools and fuel, and the doors on it must hold their proof while letting fitters and vehicles pass through. A glazed leaf lets the staff see the yard beyond it without opening the leaf, and the pane takes the same proof as the leaf, because the leaf and the glass are proved as one doorset.

The fuel and the vehicles in a workshop carry a fire load of their own, and the doors between the workshop and the stores must hold the fire where it starts. A leaf between the two takes the period the stores demand, because a fire that starts among the parts must stay among the parts while the fitters move out.

For the windows set into the same walls, the fire rated windows guide names what the pane must hold, and the fire rated glass cost guide works through what the glass itself adds to the order.

Stores and the yard gate: the doors behind the workshops

The stores hold the heaviest fire load in the depot, because the parts and the fuel sit there in boxes and on racks all day. A stores leaf takes FD60, and the period follows the load in the room rather than the size of the building.

Vehicles reach the depot through the yard gate and the loading bay, so the doors there stand open for deliveries. A leaf that stands open through the day takes a hold-open device proved to BS EN 1155, which lets the leaf go the moment the alarm sounds. A leaf wedged open with a pallet holds nothing back when the fire comes.

The doors that take the deliveries in are covered in the loading bay doors guide, and the same care is taken with a depot loading bay as with a warehouse bay.

The office and the plant room: the rooms that keep the depot running

The office holds the job sheets and the records, and the leaf that guards it takes the period the room beside it takes. An office leaf takes FD60 where the office sits beside the workshops, because a fire that starts among the vehicles must not reach the records.

The plant room takes the same care, because the machinery and the electrical boards sit behind its doors all day, so a plant room leaf takes FD60. The plant room door requirements guide sets out what the plant room leaf must do.

Some depot leaves must hold fire back and hold an intruder out as well, so they carry both proofs on one doorset. Under LPS 1175 Issue 8.2 of September 2024 the forced entry categories run at three, five and ten minutes, under the names B3, C5 and D10. The LPS 1175 vs PAS 24 guide puts the two ratings side by side, the keeping an LPS 1175 rating valid guide names the faults that break a rating after fitting, and the fire and security doors dual certification guide shows how one doorset carries both proofs.

The way out when the alarm sounds: depot escape routes

The alarm in a depot turns every driver and fitter toward the exit the plan names, so the passage must stay free of pallets, bins and parked vehicles. A leaf on that passage yields to a single push, and it yields whether the lights are on or the power has gone.

A route door carries a smoke rating beside its fire period, and BS EN 1634-3 gives it: Sa where the smoke is at room temperature, S200 where it is at 200 degrees. Either mark works only where the seal meets the frame all the way round, because smoke reaches the route ahead of the flames. The smoke control doors guide works through how the doors hold smoke back while people move past them.

No leaf on one route holds for less time than the rest, because the shortest proof among them sets how long the whole route lasts. A leaf that gives way sooner than its neighbours ends the route with it, so every leaf on the route takes the period the route needs. The fire door regulations stadiums guide shows the same care taken with crowds leaving a stand.

Position Door Period What to check
Workshop Steel leaf FD60 Leaf, lock, seals
Stores Steel leaf FD60 Leaf, lock, seals
Office Steel leaf FD60 Leaf, lock, seals
Plant room Fire leaf FD60 Leaf, seals, gap
Public route Fire leaf FD30 Leaf, bar, closer
Back of house Steel leaf FD60 Leaf, closer, seals

What keeps the period: closers, seals and gaps on depot doors

The closer on a depot leaf works harder than the closer on most other doors, because fitters pass through it all day with tools and parts. Under BS EN 1154 the smallest closer power on a fire door is EN 3, and the check is to open the leaf and watch it shut on its own. A closer that has lost its pull leaves the leaf standing open after the fitter has passed.

A 4 mm gap is kept beside the leaf, so the leaf swings free and the seal can close the opening once the leaf shuts. Once the heat passes 200 degrees the intumescent seal swells and closes the gap, unless a coat of paint over the seal stops it swelling. A seal that has slipped from its groove is noted against its door on the day it is found, with the part and the date beside it.

The hinges take the weight of the leaf through every swing of the day, and a hinge that works loose lets the leaf sink until it drags on the floor and smoke slips through the gap it leaves at the top. What the lock the key turns must do is set out in the fire door hardware guide, and the fire door closers guide covers closer sizes and fitting.

Ordering for a depot: one list for every door

The whole depot order sits on one list, and each door has its own line with the leaf, the period, the lock and the closer beside it, so what arrives matches the room it was ordered for. A list that names one leaf for the whole depot leaves the fitter to guess which part takes which period, and a leaf in the wrong workshop guards the wrong thing.

Every door on the order carries its own figure, and the figures are laid beside the schedule one door at a time before anything is signed, because a door with no figure beside it still turns up on the invoice, and a lock ordered after the doorset costs more than the same lock ordered with it. The how to specify security doors guide lists what the schedule must hold for every door, and the security door cost factors guide sets out what each step up the grade adds to the figure.

Once a week the depot manager walks the yard and tries the leaves in turn, starting at the office and finishing at the loading bay. A leaf that drags, a seal out of its groove and a closer that has lost its pull are each put down against the door where they were found, on the day they were found, and the repair is booked while the fault is still small. The record stays with the depot file, and what the visit should cover is set out in the fire door inspection checklist.

A depot leaf holds only as long as the workshops behind it and the route beside it, so the period, the release and the closer must all sit on the same list.

What period should a depot door carry?

FD30 or FD60, proved to EN 1634-1. The workshop and the stores take FD60 while the public route takes FD30, so the period follows the room, and the letters beside the minutes say what the doorset held back.

Can one leaf hold fire and forced entry?

Yes. A doorset that passed the fire test and the forced entry test together carries one report for both jobs.

Do depot doors need panic hardware?

Yes. A panic bar proved to BS EN 1125 sits on every leaf on the way out, across at least 60 percent of the leaf, so the latch throws with one push even when the person reaching it has never used the door before.

What grade should a depot stores door carry?

B3, C5 or D10 to LPS 1175, with the grade rising as the value behind the leaf rises, so the stores take a higher category than the yard gate.

Who checks the depot doors?

The depot manager walks the round that covers every door, and each visit goes into the record the depot keeps.

Specifying doors for a depot?Send the door list and the period each door must hold for a tested door quotation.
Get a free quote

Related

More in guides for specifiers

10 mistakes when specifying certified security doors 10 steps to specify an LPS 1175 door Acceptance and Snagging of a Security Door or Barrier Job Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire door regulations for commercial buildings in the UK Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Doors and Gateway 2 in Higher-Risk Buildings Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to keep an LPS 1175 door rating valid after installation How to Specify Fire Doors in a Housing Tender How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Programming a Security Door and Barrier Package on a Live Site Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Server Room Doors Explained Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →

Products

One supplier for the whole building envelope

Ready to specify your project?

Free assessment, written specification and test evidence. Reply within one working day.