Server Room Doors Explained

Server room doors must resist forced entry, hold fire for the compartment rating, and keep shielding and cooling intact. What to specify for each demand.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

A server room door has three jobs at once. It must resist forced entry long enough to matter, hold back fire for the rating the compartment needs, and keep the room sealed against the air, dust and signals that the equipment inside cannot tolerate. A door that does one of those jobs and fails the other two leaves the room open in the way that matters most.

The mistake is to treat the door as a leaf. The leaf is one part of a doorset: leaf, frame, fixings, seals, lock, closer, hinges and, where the room is shielded, the conductive gasket that keeps the envelope continuous when the door closes. The test evidence describes the doorset as a whole, and the rating belongs to that whole, not to the leaf alone.

The room itself decides the specification. A comms room in a small office, a data hall in a colocation site and a control room in a critical facility hold assets of different value, face different threats and sit under different rules. The sections below work through the demands in turn: security, fire, shielding and the environment the door sits in.

  • SR3 and aboveData hall doorsets to LPS 1175, corridors SR2 or above
  • EI 30 to EI 120Fire ratings for steel doorsets, integrity and insulation
  • dB attenuationShielding specified by attenuation over a frequency range
  • EN 50600The data centre standard behind the wider site design

The server room door is a doorset, not a leaf

Every rating on a server room door belongs to a doorset that was tested together: leaf, frame, fixings, seals and hardware in one construction. Swap one hinge, one lock or one seal for a part with no test evidence, and the doorset on site is no longer the doorset that was tested. The certificate does not follow the swap, and neither does the rating. Ask for the test evidence that names the doorset as supplied, and check that every part on the schedule matches it.

The wall matters as much as the door. A rated doorset fitted into a weak wall, with fixings that miss the structure, or with a frame packed out to fit a larger opening, is outside its evidence. The rating covers the assembly and the opening around it, not the leaf on its own. Name the wall construction, the frame fixings and the glazing beside the door in the same specification, because a strong door in a weak line protects nothing. For the wider family of doorsets and how each type is chosen, see our types of security doors guide.

Size is decided at design stage, not on delivery day. Racks, crates and replacement servers must pass through the door, and a leaf too narrow forces equipment through the wrong route, or through the door with the leaf taken off its hinges. Measure the largest item the room will ever receive, add the clearance the handlers need, and write the clear opening into the schedule. A door that cannot admit the equipment it guards will be wedged open, and a wedged door is a door that protects nothing.

Security rating: matching the door to what the room holds

The forced entry rating follows the value of what the room holds. The zone model on this site sets the pattern: corridors take LPS 1175 SR2 or above, and the data hall takes SR3 and above, with logged and supervised access. A comms room in a small office may need less than a data hall in a colocation site, and the threat assessment for the site decides the final rating for each opening. Never write one rating for every door on the site; match each doorset to its own room. Our data centre physical security by zone guide sets out the zone model in full, and our data centres sector page gives the wider threat picture.

An LPS 1175 rating states the tool category and the attack time the doorset resisted in test. The higher the class, the longer the delay and the heavier the tools the test used. Name the standard, the issue and the class in the specification, so the supplier cannot answer with an older issue or a lower class. PAS 24 sets a baseline for a secure doorset, and a server room usually needs more than the baseline, which is why an LPS 1175 rating is named instead. For the ratings in full, see our LPS 1175 page.

Locking must work with the access system, not against it. Readers, electric strikes and locks are part of the tested doorset, and a lock changed after the test takes the doorset outside its evidence. Electric locking must release on fire alarm, so the door never traps people inside the room. A door that cannot be opened from the inside in a fire is a door that fails its first duty, whatever its security rating. For how the ratings sit together on one doorset, see our dual certification guide.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

Fire rating: integrity and insulation for the compartment

Fire performance is tested to BS EN 1634-1 and classified by what the doorset holds back and for how long. E is integrity: the door stops flames and hot gases passing through. EW adds a limit on radiated heat. EI adds insulation: the temperature on the unexposed face stays within limits, so the heat alone cannot ignite what sits on the other side. The periods are 30, 60, 90 and 120 minutes, and the fire strategy for the building names the period each opening needs. For the classifications in full, see our fire ratings page.

A server room is often its own compartment, because the room holds a high fuel load of cabling and equipment and because the loss of the room can stop the whole building working. The fire strategy decides the rating, and the doorset must carry it. A door rated EI 60 in a compartment that needs EI 90 is a door that fails the strategy, even if it is the strongest door on the corridor. Check the strategy before the order, not after the doors arrive.

Fire and security meet on the same doorset, and both certificates must describe the same construction. A steel doorset that carries an EI rating and an LPS 1175 rating has shown both performances on one build, and that is the only build the two certificates cover. Our fire rated steel doors page covers the steel doorset that carries both, and the dual certification guide works through the overlap in detail.

The seals and the closer are part of the fire performance. Intumescent seals expand when heat reaches them and close the gap around the leaf, and the closer shuts the leaf and drives the latch home after every opening. A closer that cannot latch the door leaves the compartment open, and a seal painted over cannot expand. For the closer, see our fire door closers guide, and for the rest of the hardware, see our fire door hardware guide.

Shielding continuity: where the door meets the envelope

Some server rooms must also keep signals in or out. RF shielding is specified by attenuation in dB over a frequency range, agreed with the consultant before design begins. EMP shielding is specified the same way, as attenuation across the frequencies of concern. The numbers come first; the construction follows from them. Every element of the room must be treated, because the room performs only as well as its weakest penetration, and the door is usually the weakest penetration of all.

A standard door, however heavy, will not do in a shielded room. The room is lined with a conductive material, commonly copper or steel sheet, with seams sealed so the lining behaves as one continuous shell. The door must be a purpose-built shielded door with conductive gaskets, so the envelope stays continuous when the door closes. A gap at the leaf edge, a worn gasket or a hinge that breaks the seal is a hole in the shield, and signals pass through a hole whatever the walls achieve. Our RF shielding page sets out how shielded rooms are built, and our EMP shielding page covers the pulse case, where every power and signal entry is filtered and every penetration is treated.

Every penetration needs the same treatment as the door. Ventilation passes through waveguide vents that pass air but not signals. Power and signal lines are filtered where they enter, at a single defined entry point. Cable runs inside the room are kept short, and services enter at one point so the envelope has a single boundary to defend. A penetration added later, drilled through the lining for a new cable or a new fixing, breaks the envelope until it is treated and the room is re-tested. For the difference between a simple cage and a specified room, see our Faraday cage versus RF shielded room guide, and for the standards and testing behind the attenuation figures, see our RF shielding standards and testing guide.

Air, cooling and dust: the door in the airflow path

Servers produce heat, and cooling airflow is part of the room design, not an afterthought. The door must not block the cooling path, and it must not become the route that conditioned air escapes through. Where air must pass through the door itself, the opening has to be part of the tested doorset. In a shielded room that means a waveguide vent, which passes air and blocks signals. In a fire rated room it means a vent that was part of the fire test. A vent cut into the leaf after the test voids the fire evidence, and a vent cut into a shielded door breaks the envelope. Name the airflow route in the specification, and never cut the leaf on site.

Air sealing matters in the other direction too. Gaps around the leaf let dust in and let conditioned air out, and dust on live equipment is a fault waiting to happen. Seals around the leaf and a threshold seal at the bottom keep the room closed, and the closer makes sure the door returns to closed after every entry. A door that is propped open for convenience defeats the cooling design, the dust control and the fire compartment at the same time. If staff prop the door because the latch is stiff or the closer is too strong, fix the hardware, not the door.

Where the room is cooled and the corridor is warm, condensation is the quiet risk. A cold steel leaf in warm humid air can sweat, and water on the leaf runs down to the threshold and the floor. Ask about a thermally broken doorset where condensation is a risk, which limits the cold path through the leaf. Our thermally broken doors page covers the product, and the same question belongs in the specification for any cooled room.

Access control and the audit trail

Only named people should enter a server room, and the door is where that rule is enforced. Readers, fobs, PIN keypads, fingerprint or facial recognition and mobile credentials can all drive the release, and the usual choice is whatever the site already uses, so one credential opens the doors the person is allowed through and no others. Visitors and contractors get temporary credentials with a time limit, and an intercom at the door lets the person inside admit a guest without leaving the room. For the wider entrance control picture, see the data centre zone guide.

Every entry should be logged. The audit trail records who entered, when, and through which door, and it is reviewed, not just stored. Access is removed when a person leaves the organisation or changes role, and the review catches the credential that should have been cancelled. A log that nobody reads is a record, not a control. Where the room holds the highest value assets, an interlocked portal admits one verified person at a time and stops tailgating at the door itself. Our security portals page covers the product.

Two alarms belong on the door: door held open and door forced. A door held open beyond its normal time warns that the room is standing open, and a forced door warns that the lock has been attacked. Both alarms should reach the person who can act on them, not just a panel nobody watches. And the release must be fail-safe: on fire alarm or power failure the door releases to free exit, so nobody is trapped inside the room.

What the specification must name

A specification that leaves the rating to interpretation will be answered with the cheapest doorset that fits the words. Name the standard, the issue, the class and the doorset: LPS 1175 with its issue and rating, the fire class and period to EN 1634-1, and the shielding attenuation target with its frequency range where the room is shielded. Name the hardware by model, not by type, and name the evidence that must arrive with the order. For the discipline behind the schedule, see our how to specify security doors guide.

One doorset, all ratings. The fire certificate and the security certificate must describe the same construction, and the shielding attenuation must have been verified on a doorset of the same build. Ask for both certificates against one identical specification before the order is placed, and ask for the test reports behind them. A certificate that describes a different doorset is a certificate for a different door, and it proves nothing about the one on site.

Installation belongs in the specification too. Name the wall construction, the frame fixings and the opening the door is fitted into, because the rating follows the installation, not the delivery note. Record any change in writing with its effect on the test evidence, and keep the record with the building records, so the next person to work on the door knows what must not change.

Testing, handover and keeping the door working

Test the door on completion, not at the next inspection. Open it to several positions, release it, and confirm it closes fully and latches every time, without help and without slamming. Test the access control: a valid credential opens it, an invalid credential does not, and the alarms report a held door and a forced door. Where the room is shielded, the attenuation is verified by survey on completion, and the survey is the evidence the room performs as specified.

The handover pack carries the proof. It should hold the certificates for every rating the doorset carries, the hardware schedule listing every lock, hinge, closer and seal as tested, the test reports, the installation record showing the fixings and the wall, and the inspection log with dates, findings and the name of the person who checked the door. A door with its evidence in order is a door that can be checked, repaired and kept.

Keeping the door working is an inspection routine, not a repair call. Check the hinges, the seals, the closer and the lock at every visit, and check the shielding gaskets where the room is shielded: a gasket that has flattened or torn breaks the envelope, and a seal painted over cannot expand in a fire. Replace worn parts with the same part or a part with the same test evidence, and record every change. For the changes that can cost a door its rating, see our guide to keeping an LPS 1175 rating valid, and for planned servicing and records, see our maintenance page.

Demand What to specify Standard to name What it protects
Forced entry LPS 1175 doorset, SR2 corridors, SR3 data hall LPS 1175 Servers and data against attack
Fire EI rating to match the compartment EN 1634-1, E, EW, EI The compartment line and escape time
RF shielding Shielded door, conductive gaskets, filtered entries Attenuation in dB over a frequency range Signals kept in or out
EMP shielding Continuous envelope, filtered power and signal Attenuation across frequencies of concern Critical electronics through a pulse
Access Reader, logged entry, fail-safe release Site access policy and fire strategy The audit trail and free exit

A server room door that is never tested is a door the room relies on without evidence. Test the close, the latch, the lock and the seal, and keep the record.

Does a server room door need a fire rating?

Yes, where the fire strategy makes the room a compartment. The rating follows the strategy: E for integrity, EI where insulation matters too, for the period the compartment needs, commonly 30, 60, 90 or 120 minutes. Check the strategy before the order, and ask for the fire certificate against the same doorset as the security certificate.

What LPS 1175 rating does a server room need?

The zone model sets the pattern: corridors SR2 or above, and the data hall SR3 and above, with logged and supervised access. The threat assessment for the site decides the final rating for each opening, so match each doorset to its own room rather than writing one rating for the whole site.

Can a normal steel door be used in a shielded room?

No. A standard door, however heavy, will not do. A shielded room needs a purpose-built shielded door with conductive gaskets, so the envelope stays continuous when the door closes. The attenuation is verified by survey on completion, and any penetration added later must be treated and the room re-tested.

How does cooling airflow work with a sealed door?

Air passes through the door only where the opening is part of the tested doorset: a waveguide vent in a shielded room, or a vent that was part of the fire test in a fire rated room. Never cut a vent into the leaf on site. Name the airflow route in the specification, and keep the door closed so the cooling design and the dust control both work.

Who may enter the server room?

Only named people, through a credential the access system recognises, with every entry logged and reviewed. Visitors and contractors get temporary credentials with a time limit. The door must release on fire alarm or power failure, so nobody is trapped inside the room.

What a server room rating does not prove

A rating on a server room door proves one thing: the tested doorset held its rating in the test. It proves nothing else. Treat the certificate as a narrow statement, and ask what it leaves out before the order is placed.

It does not prove the door suits the zone. A data centre is divided into zones, and the door must match the zone it guards. Corridors need SR2 or above, and the data hall needs SR3 and above with logged access, so a door rated for a corridor is not rated for the hall. Ask which zone the door stands in, and specify the rating for that zone.

It does not prove fire and shielding together. A door can carry a fire rating and still break the shielding of the room, because the shielding runs through the leaf, the frame and the seals as one continuous envelope. A gap in the seal, a hinge that breaks the contact, or a leaf swapped for one without the shielding build leaves the room open to interference. The fire test and the shielding test are separate, and both must name the same doorset.

It does not prove the room stays cool. A server room door sits in the airflow path, and a leaf that blocks the cooling air or lets dust through the gaps around it works against the room it guards. Cooling and dust are checked at handover, not assumed.

It does not prove who passed through it. A server room door without an audit trail cannot say who opened it or when, and a room that holds client data needs that record.

Mistakes that break a server room door order

Most server room door orders fail in small ways. Each mistake below has the same result: a door that looks right and cannot be proved.

Mistake Why it fails What to do instead
Leaf ordered without the frame The rating belongs to the tested assembly, not the leaf alone. Order leaf, frame, seals and hardware as one doorset.
Corridor rating fitted on a data hall door A door rated SR2 cannot guard a hall that needs SR3 or above. Match the rating to the zone the door stands in.
Shielding seals left off the schedule A gap in the seal breaks the shielding of the whole room. List the seals and the contact points on every order.
Access control with no audit trail Nobody can say who opened the door or when. Log every opening and check the log.
No test report on site Without the report, nobody can check the door against what was tested. File the test report with the building records.

Keep the evidence with the door. The test report, the classification and the hardware schedule should travel with the doorset, so the fitter and the inspector can check what was bought against what was tested. For the shielding the door must keep continuous, see our EMP shielding page, and for how fire and security sit on one doorset, see our dual certification guide.

Specifying doors for a server room or data hall?Send the room, the ratings and the shielding target for a tested doorset quotation.
Get a free quote

Related

More in guides for specifiers

10 mistakes when specifying certified security doors 10 steps to specify an LPS 1175 door Acceptance and Snagging of a Security Door or Barrier Job Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire door regulations for commercial buildings in the UK Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Depots Explained Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Doors and Gateway 2 in Higher-Risk Buildings Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to keep an LPS 1175 door rating valid after installation How to Specify Fire Doors in a Housing Tender How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Programming a Security Door and Barrier Package on a Live Site Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →