Buying Security Doors and HVM Through Public Frameworks
A framework lets a buyer order security doors or barriers without a full tender. How the Procurement Act 2023 route works and what a supplier must show.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
A public framework lets a buyer place an order for security doors or barriers without running a full tender of its own. This guide explains how frameworks work under the Procurement Act 2023, who runs them, and what a supplier must show to win work through one.
- Section 45The Act’s framework definition
- Four yearsUsual maximum framework term
- Call-offThe order placed under a framework
- GCAThe largest central buyer
What a framework is, and what a call-off is
The Procurement Act 2023 defines a framework as a contract between a contracting authority and one or more suppliers that provides for the future placing of contracts by that authority with those suppliers. The future contracts are called call-offs. A framework sets out the terms under which those call-offs will be placed, including the price to be paid or how the price will be worked out.
The point is to do the heavy work once. The competition to join the framework tests the suppliers, agrees the terms and fixes the pricing method. A buyer who later needs doors or barriers then places a call-off under those terms instead of running a fresh competition from scratch.
A framework does not commit a buyer to buy anything at all. It is a route to market, not an order. The tender response checklist covers the supplier side of a public tender, and the housing tender guide covers the buyer side of the same process.
Closed frameworks, open frameworks and dynamic markets
A closed framework fixes its list of suppliers for its term. No new supplier can join once it has started. Under the Act the usual maximum term is four years, though a framework for defence or utilities can run for eight years, and a longer term is possible where the nature of the goods or works needs it, with the reason published in the tender or transparency notice.
An open framework is a scheme of successive frameworks on substantially the same terms. New suppliers can join when the framework re-opens. It must re-open at least once in its first three years and at least every five years after that, and it lasts eight years in total. The first framework in the scheme can last at most three years, and the later ones at most five years each.
A dynamic market is a list of qualified suppliers that stays open, so new suppliers can join through its life. Only above-threshold work can be placed under it. The gov.uk guidance on frameworks sets out the rules for each type in full.
| Route | How suppliers join | Longest term | When it fits |
|---|---|---|---|
| Closed framework | Once, before it starts | Four years, or eight for defence and utilities | Settled markets |
| Open framework | At each re-opening | Eight years across the scheme | Fast-moving markets |
| Dynamic market | At any time while it runs | No fixed list to close | Changing supplier base |
| Dynamic purchasing system | At any time while it runs | Under the 2015 rules | Older lists still running |
Who runs the frameworks a buyer can use
A centralised procurement authority carries out procurements for other authorities. It sets up frameworks for others to use and takes responsibility for complying with the Act when it sets the framework up. The buyer who places a call-off under it stays responsible for complying with the Act when it places that call-off.
The Government Commercial Agency is the largest centralised procurement authority in the UK. It was formed on 1 April 2026, combining the Crown Commercial Service with several Cabinet Office central commercial teams. The Crown Commercial Service name still appears in older framework documents, so a buyer may see both names for the same route.
Other centralised procurement authorities include regional purchasing bodies such as ESPO, YPO and NEPO. The gov.uk action plan for the Crown Commercial Service describes how its agreements work for buyers and suppliers.
The checks before you call off
The gov.uk Framework Practice Guide tells buyers to run pre-procurement checks first, starting with the Summarised Search on Find a Tender, which shows the levy, the suppliers on each lot, whether it is an open framework, how many small suppliers it holds, and the value against its length.
The buyer should also check that the framework was set up by a contracting authority, that the notice names the buyer as one allowed to use it, that the framework covers what the buyer needs, and that the total value of call-offs so far has not passed the estimated value in the notice.
One risk: a framework set up by a private operator and merely hosted by a small authority can leave the buyer carrying the provider’s liabilities if the framework was not set up properly. A market assessment made when the framework was set up can also go stale if suppliers have left or merged since. The Operational Requirement guide sets out how a buyer writes down what a site needs before any route is chosen.
How a call-off is placed
A call-off can be placed with or without a competition between the suppliers on the framework, and the selection process must be set out in the framework itself. Where a competition is run, the assessment must rest only on some or all of the criteria used when the framework itself was set up, although those criteria can be refined.
A call-off without a competition is allowed only in two cases: where there is a single supplier on the framework, or where the framework sets out an objective way of choosing the supplier together with the core terms of the call-off. The core terms cannot be changed except under the Act’s rules for modifying a public contract. They cover the deliverables, warranties, charges and pricing method, record keeping, indemnities, termination and variation.
A framework cannot be used to place another framework, or to place a concession contract. A direct placement cannot be used to place a call-off under a framework, and it is not needed: if a direct placement is allowed, the buyer can place the contract directly with any supplier, including one on a framework. The vehicle barrier due diligence guide shows the evidence checks a buyer runs before choosing a barrier supplier.
What the supplier must show
The Act lets a framework set conditions of participation for a call-off. Those conditions must be a proportionate way of making sure the suppliers have the legal and financial capacity and the technical ability to do the work. A condition can repeat one from the framework set-up, or add a new one for the particular call-off, such as bespoke insurance for that job.
Before a call-off is placed, the buyer must check that the supplier is not an excluded supplier. A framework cannot permit a call-off to go to an excluded supplier, so the buyer should check the central debarment list rather than rely on the check made when the framework was set up.
For security doors and barriers, the technical ability check is where the ratings sit. A supplier should be able to show the certificate and the live listing for each product. The LPS 1175 certificate guide runs through the five checks on a certificate, and the Secured by Design listing guide does the same for a scheme listing. The mixing standards guide shows the schedule mistakes that make a call-off hard to answer.
A framework is a route to market, not a shortcut past the rules. The checks still happen, they just happen at a different point.
After the call-off: who owns what
Once a call-off is placed, the buyer owns the relationship. The buyer sets the call-off key performance indicators, watches them, and tells the framework provider if a systemic problem appears. The buyer also watches the supplier’s financial standing through the life of the contract.
Contracting authorities must publish a contract notice after a call-off is placed, and buyers using a framework must link their notices to the framework provider’s notices on the central digital platform. Fees can only be charged to suppliers that have been given a call-off, as a fixed percentage of its estimated value, and no fee can be charged for access to the framework itself.
PPN 023, issued in November 2025, sets the thresholds for procurements that start on or after 1 January 2026. Central government goods and services sit at £135,018, sub-central bodies at £207,720, works at £5,193,000 and light touch contracts at £663,540. Under the same note, central government bodies must publish contracts of £12,000 or more, and other public bodies must publish contracts of £30,000 or more, on the central digital platform. The forced entry, ballistic and blast guide helps a buyer name the rating family the call-off must ask for, and the installation handover guide runs through the checks a buyer makes when the product arrives on site.
Can a buyer place a call-off with any supplier?
No. A call-off can only go to a supplier on that framework, and only for goods, services or works the framework covers.
How long can a framework run?
Four years is the usual maximum, or eight years for defence and utilities. An open framework lasts eight years in total.
What is the difference between a framework and a dynamic market?
A framework holds a fixed list of suppliers for its term, and call-offs go to suppliers on that list. A dynamic market stays open, so new suppliers can join at any time.
Must a notice be published after a call-off?
Yes. A contract notice must go out after a call-off is placed.
Can a private company run a framework?
No. Only a contracting authority can establish a framework. A private operator can only set one up as the agent of a named contracting authority.
Contact us for a free quote
Related
More in guides for specifiers
Products
One supplier for the whole building envelope
Ready to specify your project?
Free assessment, written specification and test evidence. Reply within one working day.