How to Specify Fire Doors in a Housing Tender
How to write a housing tender specification for fire doors: CPV 44221220, BS EN 1634-1 evidence, the door schedule and what a good bid shows.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
A housing tender for fire doors asks a supplier to do two things at once: supply doors that hold fire and smoke back, and prove it with papers a housing provider can file. This guide sets out how to write the specification so the bids that come back can be compared fairly.
- CPV 44221220Fire doors, the code fire door tenders carry
- BS EN 1634-1Fire test for doorsets, current edition 2014 plus A1 2018
- FD30SFlat entrance doors: 30 minutes with smoke seals
- Find a TenderCentral platform for new public tenders since 24 February 2025
Read the notice before you write a word
Start by reading how the tender was published, because that decides which rules the bids must follow. Since 24 February 2025 the Procurement Act 2023 has governed new public procurement in England, Wales and Northern Ireland, and Find a Tender is the central digital platform where new notices appear. Contracts Finder still carries notices from earlier procurements.
The value of the contract decides how much of the Act applies. For procurements starting on or after 1 January 2026, the main thresholds are £135,018 for goods and services bought by central government and £207,720 for other public bodies, with works at £5,193,000. Below those thresholds the Act still sets duties: a buyer that advertises a contract must publish a tender notice on Find a Tender from £12,000 for central government and £30,000 for councils and most other public bodies, including housing associations that count as public bodies.
Name the rating in the European form
Write the rating as the test proves it. A fire door is tested to BS EN 1634-1, then classified under BS EN 13501-2, where E means integrity, EW means integrity with limited radiation, and EI means integrity with insulation, followed by the minutes: E30, EI30, EI60. The familiar FD30 and FD60 labels come from the older British test, BS 476-22. Our fire ratings guide sets out E, EW and EI in plain terms.
That dual position is ending. References to BS 476 for fire resistance are being removed from Approved Document B in England on 2 September 2029, after which only the European classifications will be accepted for new building work. A door tested to BS 476 and supplied before that date stays lawful. A tender written today for work that will run past 2029 should ask for BS EN 1634-1 evidence, so the doors it buys are proved by the standard that remains.
Put the whole doorset on the specification
The rating belongs to the complete assembly exactly as tested: leaf, frame, seals, ironmongery and glazing. A tender that names the leaf and leaves the frame to the bidder will get bids that cannot be compared, because the frame, the fixings and the seals are part of what the test proved. Our fire rated steel doors range shows what a tested steel doorset carries.
Write every part into the specification. Name the closer, the hinges, the lock, the letterbox and the seals, and the glass and its beads where the door is glazed. A part swapped after the test, or a lock changed for a different model, can break the tested construction, so the specification should say that any change from the tested doorset needs evidence before it is accepted. Where the opening also needs security, say so on the same line: the LPS 1175 result says nothing about fire, and the fire result says nothing about forced entry. Our dual certification guide covers how the two ratings sit together.
Ask for the evidence by name
A tender should name the evidence it wants, not leave the bidder to guess. Ask for the certificate for the doorset, the label on the leaf, and the test report behind the rating. The certificate should name the sizes, configuration, locks and fixings the test covered, and the doors that arrive should match them. Our fire door certification guide sets out what each paper should show.
Third-party certification schemes give the buyer a register to check against. Product schemes such as Certifire, BM TRADA Q-Mark and IFC Certification certify the doorset itself, and installer schemes such as FIRAS and BM TRADA Q-Mark certify the company that fits or repairs it. Ask for the certificate number and check it on the scheme’s public register, because a label that cannot be traced proves nothing. Ask for the installer’s evidence too: a doorset fitted outside its tested scope is not a certified doorset.
Write the door schedule block by block
The schedule is the heart of the tender. List every block, and for each block list every opening with its rating, size, wall type and ironmongery. Flat entrance doors take FD30S with a self-closing device. Communal doors take the period the fire strategy names. Plant room and riser doors take the period for the fire load behind them. Our flat entrance doors guide sets out the FD30S door, the closer and the seals for a block.
Build the schedule from the survey, not from memory. A survey that records each door by its opening gives the bidder a list that can be priced door by door, and a tender that prices door by door can be compared door by door. Where the survey found doors that were never checked because access was refused, the schedule should say so, and the tender should ask the bidder how it will handle access to flats. Where a wall type is unknown, say so and ask the bidder to confirm it on its own survey.
Set the evaluation: what a good bid shows
The evaluation should test the bid against the specification, not against the lowest figure. A good bid shows the certificate and test evidence for the doorset it offers, names the sizes and configuration the test covered, and matches them to the openings on the schedule. A bid that offers a different doorset without evidence has not answered the specification. Our fire door cost factors guide sets out how to read a quotation against a schedule.
Look for the plan behind the bid. The bidder should show how it will phase the work block by block, arrange access to flats, keep escape routes clear while work is under way, and record each door as it is done. Social value and resident care belong in the evaluation too: the work happens in occupied homes, so ask how the bidder will tell residents what is happening, handle a resident who refuses access, and leave each flat at the end of the day.
After the contract is signed: hold the file
The work does not end when the last door is fitted. Each door should be checked against its certificate before it is accepted: size, configuration, locks and fixings should match the test evidence, and the self-closing device should shut the door fully from any angle. A door that arrives with a different lock or size from the one tested is not the door that was ordered.
The file the provider holds after handover should contain the certificate, the label and the test evidence for every doorset, the record of the fitting for each door, and the survey record the tender was built from. That file is also the starting point for the checks the regulations require: communal fire doors checked at least every 3 months and flat entrance doors every 12 months in blocks where the top storey is above 11 metres. Keep the file with the fire risk assessment, not apart from it: the assessment judged whether the doors were adequate, the tender bought the doors that answer that judgement, and the file proves the doors fitted are the doors specified.
Which CPV code do fire door tenders carry?
CPV 44221220, fire doors. The code appears on recent public fire door tenders, including housing association replacement projects, and searching by it finds tenders whose titles do not name fire doors at all.
Where do housing fire door tenders appear?
On Find a Tender, the central digital platform for new public procurement since the Procurement Act 2023 came into force on 24 February 2025. Contracts Finder still carries notices from earlier procurements, so a weekly search should check both.
What rating should flat entrance doors carry?
FD30S: 30 minutes of fire resistance with smoke seals. That is the rating the government guidance names for flat entrance doors in purpose-built blocks, and it should be on the schedule for every flat entrance.
Is BS 476 evidence still accepted?
Yes, until 2 September 2029, when references to BS 476 for fire resistance are removed from Approved Document B in England. After that date, new building work accepts only the European classifications.
What evidence should a bidder supply?
The doorset certificate, the leaf label and the test report, with the sizes and configuration the test covered. Ask for the certificate number, look it up on the scheme’s public register, and ask for the installer’s third-party certification.
Contact us for a free quote
Related
More in guides for specifiers
Products
One supplier for the whole building envelope
Ready to specify your project?
Free assessment, written specification and test evidence. Reply within one working day.