Lead Times and Programme Risks for LPS 1175 Doors
From survey to handover: the stages of an LPS 1175 door programme, why certified manufacture takes time, and the delays that catch a programme out.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
A security door that arrives late holds the whole site programme: the opening stays open, the next trade waits, and the handover date moves. This guide walks the stages from survey to handover, explains why certified manufacture takes the time it does, and names the delays that catch a programme out.
- Issue 8.2LPS 1175 current issue, September 2024
- Gateway 212 weeks new, 8 weeks existing
- Survey firstThe stage that fixes the dates
- 28 daysConcrete curing quoted at this age
The stages from survey to handover
A doorset programme runs in order: survey, certified manufacture, site preparation, fitting, then handover with the record. No stage can start properly until the one before it is finished, and the longest stage sets the date the site can be closed.
The survey fixes the size of each opening, the condition of the wall and the way the leaf must swing. The manufacture stage builds the doorset to the rating named, with the certificate behind it. The site stage prepares the opening and the floor, and the fitting stage sets the doorset in place.
Handover is not the last hour of the job. The buyer receives the certificates, the listing checks, the fitting record and the maintenance note, and the golden thread record takes the information into the life of the building. The programming guide sets out how a security door and barrier package is planned in order, and the tender evaluation guide covers how the buyer scores the programme.
Survey: the stage that fixes the dates
The survey is the stage that decides the programme. A wall that is out of square, a floor that falls away from the opening, or a leaf that must clear a step changes the size of the doorset and the fixings it needs. A survey that misses these leaves the manufacturer guessing, and the guess comes back as a delay when the doorset arrives.
The survey also fixes the rating each opening needs. LPS 1175 Issue 8.2 (September 2024) grades the doorset from A1 to H20, and the grade sets the tool set and the time the leaf must hold. A change of grade after manufacture starts sends the order back to the start.
The buyer should ask for the survey in writing, with each opening measured and the wall condition noted, before the order is placed. The 10-steps guide runs through the specification from the first measure to the last check.
Certified manufacture: what the wait buys
A certified doorset is not made from stock and marked afterwards. The manufacturer builds the doorset to the rating named, and the certification body checks the product and the factory, then keeps checking with regular re-tests and visits to the production facility. That work takes time, and the time is what the certificate stands on.
The wait buys the link between the leaf on site and the leaf that was tested. Secured by Design certification is given only where the product range is submitted, representative products are tested, and the certification body visits the factory to see that the tested products match the range.
A buyer that asks for a certified doorset at short notice should expect the supplier to say so. The honest answer is a date the factory can meet, not a date the programme wishes for. The test report guide shows the buyer what the evidence behind a door says.
Site works and the concrete beneath the barrier
A barrier is only as good as its foundation, and the foundation is where the programme most often slips. A vehicle security barrier must be set in a foundation that holds the impact it is rated for, and the concrete must cure before the barrier is loaded. NPSA gives the curing of a standard mix as about 60% in 3 days and about 75% after 7 days. The quoted strength is the figure at 28 days.
The mix also has a temperature range it likes: between 10 and 30 degrees, and below 5 degrees the curing practically stops. A barrier set in a cold week, or loaded before the concrete has cured, may look finished and still fail when it is needed.
The NPSA project cycle runs in three stages: design, build and operate. A poor build may create weak points that are hard to spot afterwards, and the operate stage keeps the barrier in order with regular servicing. The NPSA hostile vehicle mitigation guidance sets out the cycle in full.
Gateway 2 and the building control wait
Where the doors sit in a higher-risk building, the programme must allow for Gateway 2. The test is height and use: at least 7 storeys or 18 metres, with at least 2 residential units, or a hospital or a care home. The Building Safety Regulator must approve the building work before construction starts. The wait runs to 12 weeks for a new building, and 8 weeks for work to an existing building.
That wait is a statutory determination period for a valid application, not a delivery time for the doors, and the two should not be mixed. The doors must wait for the approval before they are fitted, so the order for the doors should follow the approval, not run ahead of it.
The Gateway 2 guide explains the route for fire doors in a higher-risk building, and the golden thread guide shows the record the client must keep through design and construction.
What delays a programme
Most delays come from the same few causes. A late survey pushes every date that follows it. A change of rating or of ironmongery after the order is placed sends the manufacture back to the start. A wall that is found to be unsound once the old door is out needs a fix the programme did not allow for.
Site access is the next cause. A delivery that will not reach the opening, a lift that will not take the leaf, or a corridor that will not turn it means the doorset waits on site while the route is sorted. The installation handover guide sets out what the site must be ready for before the fitters arrive.
The last cause is the record. A handover with no certificates, no listing checks and no maintenance note is not a handover, and the sign-off waits until the papers are in place. At handover, the buyer makes the checks the acceptance and snagging guide names.
Holding the programme together
The buyer holds the programme together by asking for the dates in writing at the start: survey, manufacture, delivery, fitting and handover, with the gaps between them named. A date that is not written down is a date that slips without a trace.
Each date should name the evidence that goes with it: the survey note, the certificate, the listing check, the fitting record and the maintenance note. The golden thread must hold the information about the building in a form the next person can use: kept digitally, secure, available, and written in plain English. The gov.uk guidance on the golden thread sets out what the record must hold.
When a date slips, the buyer should ask what slipped it and what the new date is, and have the answer in writing. A programme that is written down can be re-planned; a programme that lives in a phone call has no date to hold. The in-service care guide shows how a barrier is kept in order once it is in use, and the warranty guide explains what the buyer should have in writing about defects and guarantees.
| Stage | What happens | What can slip it |
|---|---|---|
| Survey | Openings measured, wall condition noted | A wall out of square found late |
| Certified manufacture | Doorset built to the rating named | A change of grade after the order |
| Site preparation | Opening made ready, foundation set | Concrete curing in a cold week |
| Fitting | Doorset set in place | A route that will not take the leaf |
| Handover and record | Certificates, checks and note given | Papers missing at sign-off |
The longest stage sets the date. A programme that names every stage can be re-planned; a programme that names none has no date to hold.
How long does a certified doorset take?
There is no published standard lead time. Ask the supplier for the survey, manufacture, delivery and fitting dates in writing at order stage.
What fixes the programme dates?
The survey. It sets the size of each opening, the state of the wall and the rating each opening needs.
How long must barrier concrete cure?
The strength is quoted at 28 days. A standard mix reaches about 60% by day 3 and about 75% by day 7. Below 5 degrees the curing practically stops.
What is Gateway 2, and how long does it take?
The Building Safety Regulator’s approval before building work starts on a higher-risk building. New buildings wait 12 weeks, work to an existing building waits 8 weeks.
What delays a programme most often?
A late survey, a change of rating after the order, an unsound wall found once the old door is out, a delivery route that will not take the leaf, and a handover with the papers missing.
Contact us for a free quote
Related
More in guides for specifiers
Products
One supplier for the whole building envelope
Ready to specify your project?
Free assessment, written specification and test evidence. Reply within one working day.