Acceptance and Snagging of a Security Door or Barrier Job
Acceptance is the day the buyer tests the job against the order. This guide sets out what to test, what counts as a snag, and what goes in the O and M file.
- ✓Third-party test evidence with every product
- ✓Written specification you can issue to tender
- ✓Supplied and installed across the UK
Get a free project quote
Rating, written specification and budget range within one working day.
Confidential. No cost, no obligation.
Third-party tested
Evidence with every quote
UK manufactured
Made to your sizes
One accountable team
Specify, supply, install
Confidential handling
Details never shared
Acceptance is the day the buyer tests the job against the order. This guide sets out what to test, what counts as a snag, and what goes in the O and M file.
- AcceptanceThe test before the signature
- SnagA fault to put right
- O and M fileThe record the next person needs
- Sign-offWhat the risk owner accepts
Acceptance is a test, not a walk
A walk looks at the job; acceptance tests it. The difference is the list: every door and every barrier is run through the same checks, and each one passes or fails on its own.
Write the test list before the work starts, and put it in the order. Name what will be tested, what a pass looks like, and who will be there to see it. A test list written after the work is finished can only confirm what was done; one written before it shapes what is done. The programme guide sets out the order the work follows, from survey to handover.
Name the scope in the order, as the security doors specification guide sets out.
Every door, tested the same way
Start with the certificate. The installer should issue one Certificate of Conformity for the installation, naming the site and the product as fitted, with the scope it covers. Check it against the order: product name, size, hardware and fixings should match what was asked for.
Then test the door itself. Run it through the fire checks the dual-certified door guide sets out: the closer from open and from 15 degrees, the gap round the leaf, the seals unpainted and undamaged, and the hinges and ironmongery tight.
Test the hardware the way the people on site use it. Try the lock, the closer and the access control, and check the hold-open device releases on its test button where one is fitted. Where a double door needs one leaf to close before the other, check the door selector makes them shut in the right order. The same checks for the routine round are in the fire door inspection checklist.
Every barrier, tested the same way
Start with the foundation. The rating covers barrier, foundation and ground together, so ask to see the foundation design, and read it against the test report.
Then test the line as a whole, not one unit. Measure the gaps between units against the spacing in the test report: any gap wider than the tested spacing leaves the line open. Work each operable unit through its full travel, and watch it from both sides as it moves, stops and locks.
Work the controls as the people on site will: normal control first, then the manual release, then the way through when the power is out. The day the product arrives on site has its own checks in the installation handover guide.
Snag, defect and failure: three different words
Not every fault found at acceptance is the same kind of fault. A snag is a small job left undone: a fixing not tightened, a seal not seated, a label not fitted. It is put right on the day, and the unit is tested again. A defect is a fault in the product or the fitting that needs a part or a return visit: a closer that leaves the leaf ajar, a lock that does not catch, a foundation that has moved.
A failure is different again: the unit does not do the job it was bought for. A door that does not match its certificate, a barrier whose foundation was never tested with it, or a line with a gap a vehicle can use are failures, not snags. A failure is not put right on the day; it is recorded, with photographs and measurements, and the unit is marked as unproven until fresh evidence arrives.
Write each fault down with its kind, its unit and its date. After handover, the rating maintenance guide carries the same rule for security doors.
| Test | What a pass looks like | If it fails |
|---|---|---|
| Certificate against order | Product, size and hardware match | Failure, record it |
| Closer from open and 15 degrees | Leaf shuts fully both times | Defect, replace or adjust |
| Gap round the leaf | 4 mm or less, bottom as small as practicable | Defect, re-hang or re-seal |
| Barrier foundation | Matches the tested build | Failure, fresh evidence first |
| Operable unit movement | Full travel, firm lock, working release | Defect, repair and re-test |
| Seals and fixings | Undamaged, unpainted, tight | Snag, put right on the day |
The O and M file: what goes in it
The O and M file is the record the next person needs. It should hold the certificates for every doorset and barrier, the test reports behind them, the hardware schedules, the as-built record naming each opening as fitted, the foundation designs, the commissioning record, with each test and its result, and the snag list, with each fault and its fix.
Where the building is higher-risk, the O and M file is also the golden thread file. The gov.uk golden thread guidance says the client must hand over five things: the building control application information, the completion certificate application information, the completion certificate itself, control of and access to the building information, and fire safety information as well, which goes to the Responsible Person. Receipt is part of the handover: the person who takes the file confirms it arrived in a form they can use.
Hold the file in one digital place, with access guarded and versions tracked, so whoever comes next finds the truth in one file. A higher-risk building is one with at least seven storeys or standing at least 18 metres high, holding at least two homes, or a hospital or a care home. For the fire door records inside the thread, see the golden thread records guide.
Who signs, and what the signature accepts
The risk owner signs, not the fitter. The risk owner should see the tests, the snags and the O and M file, and sign only when every unit has passed or every failure carries a date for its fix. Sign nothing until the evidence is in front of you: a signature on an unproven job accepts the unknown.
The NPSA guidance on hostile vehicle mitigation sets out the project cycle the scheme follows, from design to build to operate.
The Gateway 2 guide applies the same discipline to fire doors in higher-risk buildings.
After acceptance: the first year of records
Acceptance is the start of the record, not the end of it. The first year of service is when the faults the tests missed show up: a closer that weakens, a seal that lifts, a foundation that settles after the first winter. Walk the line after the first winter, and again after heavy rain, and write down what has changed.
Keep the snag list open into the first year, and add to it. A fault found on the first walk after acceptance belongs on the same list as the faults found on the day, with the same fields: unit, fault, date, fix. The barrier care guide lists what to check on a line in service, and the dual-certified door guide covers the same discipline for doors inside the building.
Hand the file to whoever will run the building, and walk them through it. The traffic calming guide shows how the approach outside was shaped before the barrier was chosen.
The job ends when the tests pass and the file changes hands, not when the fitting is done.
What is the difference between a snag and a failure?
A snag is a minor job left undone, put right on the day. A failure means the unit misses the job it was bought for, and it stays unproven until fresh evidence arrives.
What should be tested on every door?
The certificate against the order, the closer, the gap round the leaf, the seals, the hinges and the hardware as the people on site use it.
What should be tested on every barrier?
The foundation against the test report, the gaps in the line, the full movement of each operable unit, and the controls, including the manual release and the emergency route.
What belongs in the O and M file?
Certificates, test reports, hardware schedules, the as-built record, foundation designs, the commissioning record, and the snag list.
Who signs the job off?
The person who owns the risk, after seeing the test list, the snag list and the O and M file. Sign when every unit has passed, or when every failure has a date for its fix.
Contact us for a free quote
Related
More in guides for specifiers
Products
One supplier for the whole building envelope
Ready to specify your project?
Free assessment, written specification and test evidence. Reply within one working day.