Acceptance and Snagging of a Security Door or Barrier Job

Acceptance is the day the buyer tests the job against the order. This guide sets out what to test, what counts as a snag, and what goes in the O and M file.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

Acceptance is the day the buyer tests the job against the order. This guide sets out what to test, what counts as a snag, and what goes in the O and M file.

  • AcceptanceThe test before the signature
  • SnagA fault to put right
  • O and M fileThe record the next person needs
  • Sign-offWhat the risk owner accepts

Acceptance is a test, not a walk

A walk looks at the job; acceptance tests it. The difference is the list: every door and every barrier is run through the same checks, and each one passes or fails on its own.

Write the test list before the work starts, and put it in the order. Name what will be tested, what a pass looks like, and who will be there to see it. A test list written after the work is finished can only confirm what was done; one written before it shapes what is done. The programme guide sets out the order the work follows, from survey to handover.

Name the scope in the order, as the security doors specification guide sets out.

Every door, tested the same way

Start with the certificate. The installer should issue one Certificate of Conformity for the installation, naming the site and the product as fitted, with the scope it covers. Check it against the order: product name, size, hardware and fixings should match what was asked for.

Then test the door itself. Run it through the fire checks the dual-certified door guide sets out: the closer from open and from 15 degrees, the gap round the leaf, the seals unpainted and undamaged, and the hinges and ironmongery tight.

Test the hardware the way the people on site use it. Try the lock, the closer and the access control, and check the hold-open device releases on its test button where one is fitted. Where a double door needs one leaf to close before the other, check the door selector makes them shut in the right order. The same checks for the routine round are in the fire door inspection checklist.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

Every barrier, tested the same way

Start with the foundation. The rating covers barrier, foundation and ground together, so ask to see the foundation design, and read it against the test report.

Then test the line as a whole, not one unit. Measure the gaps between units against the spacing in the test report: any gap wider than the tested spacing leaves the line open. Work each operable unit through its full travel, and watch it from both sides as it moves, stops and locks.

Work the controls as the people on site will: normal control first, then the manual release, then the way through when the power is out. The day the product arrives on site has its own checks in the installation handover guide.

Snag, defect and failure: three different words

Not every fault found at acceptance is the same kind of fault. A snag is a small job left undone: a fixing not tightened, a seal not seated, a label not fitted. It is put right on the day, and the unit is tested again. A defect is a fault in the product or the fitting that needs a part or a return visit: a closer that leaves the leaf ajar, a lock that does not catch, a foundation that has moved.

A failure is different again: the unit does not do the job it was bought for. A door that does not match its certificate, a barrier whose foundation was never tested with it, or a line with a gap a vehicle can use are failures, not snags. A failure is not put right on the day; it is recorded, with photographs and measurements, and the unit is marked as unproven until fresh evidence arrives.

Write each fault down with its kind, its unit and its date. After handover, the rating maintenance guide carries the same rule for security doors.

Test What a pass looks like If it fails
Certificate against order Product, size and hardware match Failure, record it
Closer from open and 15 degrees Leaf shuts fully both times Defect, replace or adjust
Gap round the leaf 4 mm or less, bottom as small as practicable Defect, re-hang or re-seal
Barrier foundation Matches the tested build Failure, fresh evidence first
Operable unit movement Full travel, firm lock, working release Defect, repair and re-test
Seals and fixings Undamaged, unpainted, tight Snag, put right on the day

The O and M file: what goes in it

The O and M file is the record the next person needs. It should hold the certificates for every doorset and barrier, the test reports behind them, the hardware schedules, the as-built record naming each opening as fitted, the foundation designs, the commissioning record, with each test and its result, and the snag list, with each fault and its fix.

Where the building is higher-risk, the O and M file is also the golden thread file. The gov.uk golden thread guidance says the client must hand over five things: the building control application information, the completion certificate application information, the completion certificate itself, control of and access to the building information, and fire safety information as well, which goes to the Responsible Person. Receipt is part of the handover: the person who takes the file confirms it arrived in a form they can use.

Hold the file in one digital place, with access guarded and versions tracked, so whoever comes next finds the truth in one file. A higher-risk building is one with at least seven storeys or standing at least 18 metres high, holding at least two homes, or a hospital or a care home. For the fire door records inside the thread, see the golden thread records guide.

Who signs, and what the signature accepts

The risk owner signs, not the fitter. The risk owner should see the tests, the snags and the O and M file, and sign only when every unit has passed or every failure carries a date for its fix. Sign nothing until the evidence is in front of you: a signature on an unproven job accepts the unknown.

The NPSA guidance on hostile vehicle mitigation sets out the project cycle the scheme follows, from design to build to operate.

The Gateway 2 guide applies the same discipline to fire doors in higher-risk buildings.

After acceptance: the first year of records

Acceptance is the start of the record, not the end of it. The first year of service is when the faults the tests missed show up: a closer that weakens, a seal that lifts, a foundation that settles after the first winter. Walk the line after the first winter, and again after heavy rain, and write down what has changed.

Keep the snag list open into the first year, and add to it. A fault found on the first walk after acceptance belongs on the same list as the faults found on the day, with the same fields: unit, fault, date, fix. The barrier care guide lists what to check on a line in service, and the dual-certified door guide covers the same discipline for doors inside the building.

Hand the file to whoever will run the building, and walk them through it. The traffic calming guide shows how the approach outside was shaped before the barrier was chosen.

The job ends when the tests pass and the file changes hands, not when the fitting is done.

What is the difference between a snag and a failure?

A snag is a minor job left undone, put right on the day. A failure means the unit misses the job it was bought for, and it stays unproven until fresh evidence arrives.

What should be tested on every door?

The certificate against the order, the closer, the gap round the leaf, the seals, the hinges and the hardware as the people on site use it.

What should be tested on every barrier?

The foundation against the test report, the gaps in the line, the full movement of each operable unit, and the controls, including the manual release and the emergency route.

What belongs in the O and M file?

Certificates, test reports, hardware schedules, the as-built record, foundation designs, the commissioning record, and the snag list.

Who signs the job off?

The person who owns the risk, after seeing the test list, the snag list and the O and M file. Sign when every unit has passed, or when every failure has a date for its fix.

Accepting a door or barrier job?Send the order, the certificates, and the test list the job must pass.
Contact us for a free quote

Related

More in guides for specifiers

10 mistakes when specifying certified security doors 10 steps to specify an LPS 1175 door Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire door regulations for commercial buildings in the UK Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Depots Explained Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Doors and Gateway 2 in Higher-Risk Buildings Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to keep an LPS 1175 door rating valid after installation How to Specify Fire Doors in a Housing Tender How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Programming a Security Door and Barrier Package on a Live Site Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Server Room Doors Explained Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →

Products

One supplier for the whole building envelope

Ready to specify your project?

Free assessment, written specification and test evidence. Reply within one working day.