How to Specify Fire Doors in a Housing Tender

How to write a housing tender specification for fire doors: CPV 44221220, BS EN 1634-1 evidence, the door schedule and what a good bid shows.

  • ✓Third-party test evidence with every product
  • ✓Written specification you can issue to tender
  • ✓Supplied and installed across the UK
Prefer to talk?+44 7352 267239

Get a free project quote

Rating, written specification and budget range within one working day.

ArxBridge Quote Form

Confidential. No cost, no obligation.

Third-party tested

Evidence with every quote

UK manufactured

Made to your sizes

One accountable team

Specify, supply, install

Confidential handling

Details never shared

A housing tender for fire doors asks a supplier to do two things at once: supply doors that hold fire and smoke back, and prove it with papers a housing provider can file. This guide sets out how to write the specification so the bids that come back can be compared fairly.

  • CPV 44221220Fire doors, the code fire door tenders carry
  • BS EN 1634-1Fire test for doorsets, current edition 2014 plus A1 2018
  • FD30SFlat entrance doors: 30 minutes with smoke seals
  • Find a TenderCentral platform for new public tenders since 24 February 2025

Read the notice before you write a word

Start by reading how the tender was published, because that decides which rules the bids must follow. Since 24 February 2025 the Procurement Act 2023 has governed new public procurement in England, Wales and Northern Ireland, and Find a Tender is the central digital platform where new notices appear. Contracts Finder still carries notices from earlier procurements.

The value of the contract decides how much of the Act applies. For procurements starting on or after 1 January 2026, the main thresholds are £135,018 for goods and services bought by central government and £207,720 for other public bodies, with works at £5,193,000. Below those thresholds the Act still sets duties: a buyer that advertises a contract must publish a tender notice on Find a Tender from £12,000 for central government and £30,000 for councils and most other public bodies, including housing associations that count as public bodies.

Name the rating in the European form

Write the rating as the test proves it. A fire door is tested to BS EN 1634-1, then classified under BS EN 13501-2, where E means integrity, EW means integrity with limited radiation, and EI means integrity with insulation, followed by the minutes: E30, EI30, EI60. The familiar FD30 and FD60 labels come from the older British test, BS 476-22. Our fire ratings guide sets out E, EW and EI in plain terms.

That dual position is ending. References to BS 476 for fire resistance are being removed from Approved Document B in England on 2 September 2029, after which only the European classifications will be accepted for new building work. A door tested to BS 476 and supplied before that date stays lawful. A tender written today for work that will run past 2029 should ask for BS EN 1634-1 evidence, so the doors it buys are proved by the standard that remains.

Need this specified for your project?Free rating, written specification and budget range within one working day.
Get a free quote

Put the whole doorset on the specification

The rating belongs to the complete assembly exactly as tested: leaf, frame, seals, ironmongery and glazing. A tender that names the leaf and leaves the frame to the bidder will get bids that cannot be compared, because the frame, the fixings and the seals are part of what the test proved. Our fire rated steel doors range shows what a tested steel doorset carries.

Write every part into the specification. Name the closer, the hinges, the lock, the letterbox and the seals, and the glass and its beads where the door is glazed. A part swapped after the test, or a lock changed for a different model, can break the tested construction, so the specification should say that any change from the tested doorset needs evidence before it is accepted. Where the opening also needs security, say so on the same line: the LPS 1175 result says nothing about fire, and the fire result says nothing about forced entry. Our dual certification guide covers how the two ratings sit together.

Ask for the evidence by name

A tender should name the evidence it wants, not leave the bidder to guess. Ask for the certificate for the doorset, the label on the leaf, and the test report behind the rating. The certificate should name the sizes, configuration, locks and fixings the test covered, and the doors that arrive should match them. Our fire door certification guide sets out what each paper should show.

Third-party certification schemes give the buyer a register to check against. Product schemes such as Certifire, BM TRADA Q-Mark and IFC Certification certify the doorset itself, and installer schemes such as FIRAS and BM TRADA Q-Mark certify the company that fits or repairs it. Ask for the certificate number and check it on the scheme’s public register, because a label that cannot be traced proves nothing. Ask for the installer’s evidence too: a doorset fitted outside its tested scope is not a certified doorset.

Write the door schedule block by block

The schedule is the heart of the tender. List every block, and for each block list every opening with its rating, size, wall type and ironmongery. Flat entrance doors take FD30S with a self-closing device. Communal doors take the period the fire strategy names. Plant room and riser doors take the period for the fire load behind them. Our flat entrance doors guide sets out the FD30S door, the closer and the seals for a block.

Build the schedule from the survey, not from memory. A survey that records each door by its opening gives the bidder a list that can be priced door by door, and a tender that prices door by door can be compared door by door. Where the survey found doors that were never checked because access was refused, the schedule should say so, and the tender should ask the bidder how it will handle access to flats. Where a wall type is unknown, say so and ask the bidder to confirm it on its own survey.

Set the evaluation: what a good bid shows

The evaluation should test the bid against the specification, not against the lowest figure. A good bid shows the certificate and test evidence for the doorset it offers, names the sizes and configuration the test covered, and matches them to the openings on the schedule. A bid that offers a different doorset without evidence has not answered the specification. Our fire door cost factors guide sets out how to read a quotation against a schedule.

Look for the plan behind the bid. The bidder should show how it will phase the work block by block, arrange access to flats, keep escape routes clear while work is under way, and record each door as it is done. Social value and resident care belong in the evaluation too: the work happens in occupied homes, so ask how the bidder will tell residents what is happening, handle a resident who refuses access, and leave each flat at the end of the day.

After the contract is signed: hold the file

The work does not end when the last door is fitted. Each door should be checked against its certificate before it is accepted: size, configuration, locks and fixings should match the test evidence, and the self-closing device should shut the door fully from any angle. A door that arrives with a different lock or size from the one tested is not the door that was ordered.

The file the provider holds after handover should contain the certificate, the label and the test evidence for every doorset, the record of the fitting for each door, and the survey record the tender was built from. That file is also the starting point for the checks the regulations require: communal fire doors checked at least every 3 months and flat entrance doors every 12 months in blocks where the top storey is above 11 metres. Keep the file with the fire risk assessment, not apart from it: the assessment judged whether the doors were adequate, the tender bought the doors that answer that judgement, and the file proves the doors fitted are the doors specified.

Which CPV code do fire door tenders carry?

CPV 44221220, fire doors. The code appears on recent public fire door tenders, including housing association replacement projects, and searching by it finds tenders whose titles do not name fire doors at all.

Where do housing fire door tenders appear?

On Find a Tender, the central digital platform for new public procurement since the Procurement Act 2023 came into force on 24 February 2025. Contracts Finder still carries notices from earlier procurements, so a weekly search should check both.

What rating should flat entrance doors carry?

FD30S: 30 minutes of fire resistance with smoke seals. That is the rating the government guidance names for flat entrance doors in purpose-built blocks, and it should be on the schedule for every flat entrance.

Is BS 476 evidence still accepted?

Yes, until 2 September 2029, when references to BS 476 for fire resistance are removed from Approved Document B in England. After that date, new building work accepts only the European classifications.

What evidence should a bidder supply?

The doorset certificate, the leaf label and the test report, with the sizes and configuration the test covered. Ask for the certificate number, look it up on the scheme’s public register, and ask for the installer’s third-party certification.

Ready to write your tender?Send the block list, the door schedule and the rating each opening needs.
Contact us for a free quote

Related

More in guides for specifiers

10 mistakes when specifying certified security doors 10 steps to specify an LPS 1175 door Acceptance and Snagging of a Security Door or Barrier Job Access Control Doors Acoustic Doors: Ratings and Specification After a Forced Entry Attempt: Checking a Security Door Airport Security Doors Anti-Ligature Doors for Mental Health Wards Anti-Ram Bollards Anti-ram gates and barriers: protecting vehicle entrances Arcade Security Doors Explained Automatic Doors Automatic Gates Cost Factors Automatic Vehicle Barriers Ballistic Panels Bank Security Doors Bingo Hall Security Doors Explained Blast doors: glazed vs solid and how they are rated Blast protection window film: what it does and what it cannot do Blast resistant windows: what drives the cost and how to specify them Bollard Cost Factors Explained Bollard regulations in the UK: spacing, height and depth Bookmaker Security Doors Explained Builders Merchant Security Doors Bullet Resistant Glass Cost Factors Bullet resistant glass ratings explained: BR1 to BR7 and SG classes Bullet resistant vs bulletproof glass: what the difference means Buying Security Doors and HVM Through Public Frameworks Car Park Security Doors Explained Car Showroom Security Doors Casino Security Doors Explained CDM 2015 Duties When Security Doors, Shutters or HVM Are Installed Cinema Security Doors Cleanroom Doors Cold Store Doors College Security Doors Commissioning, Handover and the O&M Manual for Security Doors and HVM Communal entrance doors for flats: Secured by Design and what to specify Community Centre Security Doors Control Room Doors Court Security Doors Crash Rated Fences and HVM Fencing Explained Data centre physical security: doors, glazing, HVM and shielding by zone Dental Practice Security Doors Depot Security Doors Explained Door Entry Systems Due Diligence When Selecting Vehicle Security Barriers Emergency Exit Doors EMP Shielding Cost Factors Explained Exhibition Centre Fire Door Rules Exhibition Centre Security Doors Factory Security Doors Faraday cage vs RF shielded room: what a business needs FB4 vs FB6 vs FB7: how to choose a ballistic rating Fire and security doors: how dual certification works Fire Compartmentation Fire Curtains Fire Door Certification Fire Door Closers Explained Fire Door Cost Factors Fire Door Duties of the Accountable Person Fire Door Gaps Fire Door Hardware Explained Fire door inspection checklist for steel and timber doors Fire Door Maintenance Fire Door Regulations Care Homes Fire Door Regulations for A and E Departments Fire Door Regulations for Airports Explained Fire Door Regulations for Bowls Clubs Fire door regulations for commercial buildings in the UK Fire Door Regulations for Dialysis Centres Fire Door Regulations for Hockey Clubs Fire Door Regulations for Hospitals Explained Fire Door Regulations for Offices Explained Fire Door Regulations for Operating Theatres Fire Door Regulations for Retail Explained Fire Door Regulations for Schools Explained Fire Door Regulations for Snooker Clubs Fire Door Regulations for Stadiums Fire Door Regulations for Student Accommodation Fire Door Regulations for Warehouses Fire Door Regulations Leisure Centres Fire Door Regulations Restaurants Fire Door Remediation Programme for Housing Providers Fire Door Rules for Badminton Clubs Fire Door Rules for Bingo Halls Fire Door Rules for Bookmakers Fire Door Rules for Bowling Alleys Fire Door Rules for Car Parks Fire Door Rules for Car Showrooms Fire Door Rules for Cinemas Fire Door Rules for Climbing Centres Fire Door Rules for Colleges Fire Door Rules for Community Centres Fire Door Rules for Cricket Clubs Fire Door Rules for Dental Practices Fire Door Rules for Depots Explained Fire Door Rules for Golf Clubs Fire Door Rules for GP Surgeries Fire Door Rules for Gyms Explained Fire Door Rules for Ice Rinks Fire Door Rules for Maternity Units Fire Door Rules for Mental Health Units Fire Door Rules for Museums Fire Door Rules for Oncology Units Fire Door Rules for Opticians Fire Door Rules for Pawnbrokers Fire Door Rules for Petrol Stations Fire Door Rules for Pharmacies Fire Door Rules for Ports Fire Door Rules for Post Offices Fire Door Rules for Prisons Fire Door Rules for Rehabilitation Centres Fire Door Rules for Self Storage Fire Door Rules for Shopping Centres Fire Door Rules for Squash Clubs Fire Door Rules for Supermarkets Fire Door Rules for Swimming Pools Fire Door Rules for Tennis Clubs Fire Door Rules for Theatres Fire Door Rules for UK Arcades Fire Door Rules for UK Casinos Fire Door Rules for UK Hospices Fire Door Rules for Walk-in Centres Fire Door Signage Fire Door Vision Panels Fire Doors and Gateway 2 in Higher-Risk Buildings Fire Rated Glass Cost Explained Fire Rated Sliding Doors Explained Fire Rated Windows Cost Factors Fire Rated Windows Explained Fire Safety Enforcement Notices and Fire Doors: What the Responsible Person Must Do Flat Entrance Doors: PAS 24 and Fire Rated Forced Entry vs Ballistic vs Blast: Which Rating a Site Needs Garage Security Doors Explained Gate Automation Explained Golden Thread Records for Fire Doors GP Surgery Security Doors Explained Gym Security Doors Explained High Speed Doors HMO Fire Doors Hospice Security Doors Explained Hospital Security Doors: Wards, A&E, Plant Hospital Security Gates Hotel Fire Doors Hotel Security Doors How to choose HVM bollards: fixed, shallow mount, removable and automatic How to keep an LPS 1175 door rating valid after installation How to specify security doors: a checklist for architects How to Verify a Secured by Design Listing How to Verify an LPS 1175 Certificate on Red Book Live How to Write an Operational Requirement for Physical Security HVM planters and street furniture: protection that blends in In-Service Care of Vehicle Security Barriers Installation Handover: LPS 1175 Doors and PAS 68 Barriers Intumescent Seals ISO 16933 explained: EXV and SB classes and hazard ratings ISO 22343 vehicle security barriers explained Keeping a Dual-Certified Fire and Security Door Valid in Service Laboratory Security Doors Layered Security for a Site: Deter, Detect, Delay, Mitigate, Respond Lead Times and Programme Risks for LPS 1175 Doors Leisure Centre Security Doors Library Security Doors Listed Building Fire Doors Loading Bay Doors Explained Lockdown and Access Control Hardware on an LPS 1175 Door LPS 1175 Gates and Grilles Explained LPS 1175 Issue 8 explained: from SR1 to SR8 to A1 to H20 LPS 1175 Roller Shutters LPS 1175 vs ASTM F2781 and Other US Ratings Explained LPS 1175 vs EN 1627: how UK and European burglar resistance ratings compare LPS 1175 vs PAS 24: which security standard does your door need? LPS 1175 Windows and Walling Explained Martyn’s Law and Places of Worship: What a Buyer Checks for Doors and Entry Control Martyn’s Law Enhanced Tier: Physical Measures and the Specifier Brief Martyn’s Law Standard Tier: Procedures, Doors and Shutters Martyn’s Law Timeline and the SIA Regulator Martyn’s Law: what premises must do and which physical measures to consider Master Key Systems MRI and RF shielded rooms: how they work and what to specify Museum Security Doors NPSA Catalogue of Security Equipment (CSE) Explained NPSA Forced Entry and Blast Guidance for Government Sites NPSA Guidance on Lockdown and Marauding Attack: What It Asks of Doors and Entrances Office Security Doors Optician Security Doors Explained Panic Hardware PAS 24 requirements for doors and windows explained PAS 68 Bollard Foundations Explained PAS 68 bollards: ratings, spacing and cost factors PAS 68 vs IWA 14 vs ISO 22343: hostile vehicle mitigation standards explained Pawnbroker Security Doors Explained Pedestrian Gates Petrol Station Security Doors Pharmacy Security Doors Planning Permission for Security Shutters, Gates and Bollards on Commercial Premises Plant room doors: fire, security and ventilation requirements Plant Room Fire Doors Port Security Doors Post Office Security Doors Explained Powder coating vs galvanising vs paint for steel Preliminary Market Engagement for Security Doors and HVM Prison Security Doors Programming a Security Door and Barrier Package on a Live Site Public-Sector Tender Response Checklist for Security Door and HVM Supply Reading a PAS 24 and SBD Door Test Report Regulation 38 Fire Safety Information at Handover for Fire-Rated Security Doorsets Replacing Security Doors in an Occupied Building Restaurant Security Doors Retail Security Doors Revolving Doors RF shielding standards and how shielded rooms are tested Rising Bollard Cost Factors Road Blocker Cost Factors Explained Road Blockers Explained Roller Shutter Cost Factors: What Drives the Price Roller shutter regulations in the UK: safety and maintenance Safe room and panic room doors: specification basics Safety Duties for Powered Doors, Gates and Barriers on Commercial Sites School Security Doors Sectional Doors Secured by Design explained: is it mandatory for doors? Secured by Design vs NPSA vs LPCB: Which One You Need Security Door Locks Security Door Maintenance Checklist Security Doors and Access for Everyone: What Approved Document M Asks Security Doors for A and E Departments Security Doors for Badminton Clubs Security Doors for Bowling Alleys Security Doors for Bowls Clubs Security Doors for Climbing Centres Security Doors for Cricket Clubs Security Doors for Dialysis Centres Security Doors for Golf Clubs Security Doors for Hockey Clubs Security Doors for Ice Rinks Security Doors for Maternity Units Security Doors for Mental Health Units Security Doors for Oncology Units Security Doors for Operating Theatres Security Doors for Rehabilitation Centres Security Doors for Snooker Clubs Security Doors for Squash Clubs Security Doors for Swimming Pools Security Doors for Tennis Clubs Security Doors for Walk-in Centres Security Doors West Midlands Explained Security Fencing Security Gates Cost Factors Explained Security shutters vs high performance roller doors Security shutters vs retractable grilles: which suits retail and commercial openings? Security Turnstiles Explained Security Window Film Security Windows for Schools Explained Self Storage Security Doors Server Room Doors Explained Shopping Centre Security Doors Smoke Control Doors Explained Smoke Curtains Specification Mistakes When Mixing LPS 1175, PAS 24 and SBD in One Tender SR2 vs SR3 vs SR4 security doors: choosing the right LPS 1175 level Stadium Security Doors Steel Door Frames Steel vs aluminium security doors: strength, ratings and looks Steel vs timber fire doors: which suits your building? Student Accommodation Security Doors Substation doors: security, ventilation and specification Supermarket Security Doors Telescopic Bollards Tender Evaluation Criteria and Scoring for Security Doors and HVM The Scope of a Maintenance Contract for Security Doors and Barriers Theatre Security Doors Thermal and Weather Performance of External Security Doorsets Thermally broken steel security doors: U-values and certification Traffic Calming as Hostile Vehicle Mitigation Transport hub security requirements Turnstile Cost Factors Explained Turnstile vs speed gate vs security portal: choosing entrance control Types of security doors for commercial buildings University Security Doors Explained Vehicle Dynamics Assessment: What It Tells the Buyer Before a Barrier Is Specified Warehouse Security Doors Explained Warehouse Security Gates Warranty, Defects Liability and Guarantees for Security Doors and Barriers What affects the cost of a bullet resistant door What affects the cost of a high-security door in the UK Window Security Bars View all →

Products

One supplier for the whole building envelope

Ready to specify your project?

Free assessment, written specification and test evidence. Reply within one working day.